> For the complete documentation index, see [llms.txt](https://greenstarresources.gbca.au/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.0-rev-c/categories-and-credits/nature/35-or-impacts-to-nature.md).

# 35 | Impacts to Nature

Points: 2

## <mark style="color:$primary;">Outcome</mark>

Ecological value is conserved and protected.

## <mark style="color:$primary;">Criteria</mark>

<mark style="color:$success;">**Minimum Expectation — Nil**</mark>

* [#id-35.0.1-site-ecological-value](#id-35.0.1-site-ecological-value "mention"): The building was not built on, or significantly impacted, a site with a high ecological value.
* [#id-35.0.2-managing-light-pollution-impacts](#id-35.0.2-managing-light-pollution-impacts "mention"): The building's light pollution has been minimised.
* [#id-35.0.3-wetland-management-plan](#id-35.0.3-wetland-management-plan "mention"): There is ongoing monitoring, reporting, and management of the site's wetland ecosystem.

<mark style="color:$success;">**Credit Achievement — 2 points**</mark>

In addition to the *Minimum Expectation:*

* [#id-35.1.1-protecting-ecological-values](#id-35.1.1-protecting-ecological-values "mention"): The building's design and construction conserves existing natural soil, hydrological flows, and vegetation elements.
* [#id-35.1.2-retaining-high-biodiversity-values](#id-35.1.2-retaining-high-biodiversity-values "mention"): If deemed necessary by an Ecologist, at least 50% of existing site with high biodiversity value is retained.

***

## <mark style="color:$primary;">Additional information</mark>

#### Stage implementation

**Strategy** | **Brief** | **Concept** | **Design** | Tender | Construction | Handover | Use

#### Synergies with other credits

* Nature Connectivity
* Biodiversity Enhancement
* Waterway Protection
* Nature Stewardship

#### Sustainable Development Goals

* **Goal 14:** Life Below Water
* **Goal 15:** Life on Land

#### Relevant reporting initiatives

* GRESB

***

## <mark style="color:$primary;">Requirements</mark>

### <mark style="color:$success;">Minimum Expectation</mark>

The project must comply with **all three** of the following criteria:

* Site Ecological Value
* Managing Light Pollution Impacts
* Wetland Management Plan

#### 35.0.1 Site Ecological Value

This requirement is met where:

* At the date of purchase or option contract, land clearing does not occur on the site as a result of the building, infrastructure, or construction works on the following:
  * Old-growth forest
  * Prime agricultural land
  * Any wetland listed as being of 'High National Importance'
  * Aspects considered 'Matters of National Environmental Significance' listed under the Environmental Protection and Biodiversity Conservation Act (1999) regardless of whether they have been referred to the Federal Environmental Minister for consideration and assessed as a 'controlled action' or not
* If the project site is adjacent, within 100 meters, or contains the above and these are being protected, the construction and future operations of the site takes measures to reduce their impact to the above as follows:
  * Both the Waterway Protection Credit Achievement and the Credit Achievement for this credit (Impacts to Nature) is met
  * The light pollution impacts are managed
  * Where the site is next to a wetland (as above), by also putting in place Wetland Protection Measures

This requirement applies to the condition of the site that existed at the date of site purchase or option contract (previous condition of the site).

In cases where the site has been owned by the current owner for more than five years (from the project's Green Star registration date), the requirements are applied to the state of the site that existed at least five (but not more than ten years) prior to the project's Green Star registration date.

Where the previous condition of the site is unclear, a qualified Ecologist shall assess the site and decide of its ecological value at the approximate time of purchase.

#### 35.0.2 Managing Light Pollution Impacts

#### *Light pollution to neighbouring bodies*

The project team must demonstrate that all outdoor lighting on the project complies with AS/NZS 4282:2019 Control of the obtrusive effects of outdoor lighting.

The conditions apply to all boundaries, apart from boundaries with roads. The boundary shall be taken as the site boundary, with no setback and no consideration of the location of adjacent buildings (i.e., worst-case scenario).

The following values from Table 2.1 of AS/NZS 4282:2019 must be applied:

* For Class 2 buildings (residential), the compliance is for columns 4 and 5 as per Table 2.1 of AS/NZS 4282:2019
* For Class 3 to 9 buildings (non-residential), the compliance is as per column 3 as per Table 2.1 of AS/NZS 4282:2019

The system must comply with both pre- and post-curfew requirements.

#### *Light pollution to night sky*

It must be demonstrated that one of the following specified reductions in light pollution has been achieved by the project:

* Control of upward light output ratio (ULOR)
* Control of direct illuminance

This covers all external lighting of a project. In addition to other types of external lighting, for the purposes of this credit, luminaires inside glazed atria and those on the uppermost (uncovered) deck of an outdoor car park are considered external.

**Control of Upward Light Output Ratio (ULOR)**\
For this option, the project team must demonstrate that no external luminaire on the project has a ULOR that exceeds 5%, relative to its actual mounted orientation. Project teams must demonstrate that the ULOR provided or calculated in the documentation, is relevant to the as-installed orientation of the luminaire.

**Control of Direct Illuminance**\
For this option, the project team must demonstrate that direct illuminance from external luminaires on the project produces a maximum initial point illuminance value no greater than:

* 0.5 Lux to the site boundary
* 0.1 Lux to 4.5 metres beyond the site into the night sky, when modelled using a calculation plane set at the highest point of the building

Calculations shall be in accordance with AS/NZS 4282:2019.

The calculation plane must cover the area between the site boundary and building façade or vertical service to be illuminated. The horizontal calculation plane shall be set at the top of the building fabric, excluding spires. Calculation plane grid points shall have a 0.5m spacing. All illumination results shall be reported to within 2 decimal places.

#### 35.0.3 Wetland Management Plan

The site-specific Wetland Management Plan must be prepared by a qualified Ecologist or other qualified professional and include requirements for ongoing quarterly monitoring, annual reporting, and management of the wetland ecosystem for a minimum of five years. The plan must be exhibited to the public on the applicant's website or the local council's offices or library for a minimum of 24 months.

### <mark style="color:$success;">Credit Achievement</mark>

In addition to the *Minimum Expectation*, the project must comply with **both** of the following criteria:

* Protecting Ecological Values
* Retaining High Biodiversity Values

#### 35.1.1 Protecting Ecological Values

#### *Context report*

The project team must demonstrate how they have attempted to understand their site's historical and current ecological context by documenting the site's current ecological values by type and biomass. This includes terrestrial and aquatic ecological values, geologic features, and soils (including interaction with living things). When determining biodiversity value, the project must reference local, regional, state, and national priorities and strategies.

The project should use this investigation as a foundation to appropriately identify if there is potential for any future ecological value to be incorporated on site.

#### *Protecting ecology*

Based on the understanding of the site, the project team must show how ecological values will be protected including:

* The proportion of existing vegetated area being retained and the biodiversity value of this area, including identifying species names.
* Identifying local and regional threats and mitigation requirements.
* Listing active management strategies to be employed to protect the integrity of ecological values throughout the project planning, construction, and occupancy.
* Documenting the community engagement process, and outline risks and opportunities to enhance the site.
* Detailing consultation outcomes with local stakeholders including Aboriginal or Torres Strait Islander groups and environmental groups.

#### 35.1.2 Retaining High Biodiversity Values

Where the area has been deemed an area of high biodiversity value by an assessment undertaken by an ecologist, the project must retain at least 50% of this area contiguously.

The project team must then provide a narrative as to how the following impacts to nature and the community have been mitigated:

* Light and noise pollution (this is met if required for the Minimum Expectation)
* Habitat disturbance and connectivity (deemed met if Biodiversity Enhancement and Nature Connectivity credits are achieved)
* On-site and downstream water quality (Deemed met if Waterway Protection credit is achieved)
* Migratory paths of insects, birds, or other species
* Two local issues appropriate to the project site (e.g., pest management and groundwater)

Consideration must be given to these impacts during demolition, siteworks, construction, or future occupation.

Where no existing biodiversity is identified through the process outlined above, the project team is not required to provide a narrative to describe how the listed impacts to nature and the community have been mitigated, but instead how the project will add biodiversity value to the site.

***

## <mark style="color:$primary;">Alternative pathways</mark>&#x20;

Where there are alternative pathways that a project can follow to achieve the credit, or sector specific alternatives.&#x20;

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Alternative pathways</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Clarifications</mark>

Where GBCA have clarified any requirements of the credit criteria. This information is additional and it is not complusory to apply.

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Clarifications</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Submission content</mark>

#### Submissions for this credit must contain:

* **Submission form** through Green Star Online
* **Evidence** to support claims made in the submission

#### Recommended evidence:

**Inclusive Design**

* Extracts from the Development Application
* Zoning Plans
* Light pollution
  * As Built drawings indicating the location of all external luminaires and showing the aiming point and mounting orientation of\
    all external luminaires
  * Luminaire schedule for all external lighting, nominating the type, lighting distribution and quantity of each luminaire and\
    including the relevant photometric data such as ULOR
  * Calculation Plots for all external lighting, showing that all grid points on the calculation plane return compliant Lux values
  * Excerpt from lighting control system, or similar, demonstrating automatic deactivation of lights, based on external lux levels,\
    where deactivation is required to achieve compliance
* If triggering the wetland requirements:
  * Wetland Management Plan
  * Evidence as per Waterway Protection credit
* Ecological assessment report
* Evidence that 50% of the site has been retained:
  * Narrative from Ecologist
  * As built drawings

Alternate documentation can also be used by project teams to demonstrate compliance.

Refer to the [Guidance for Submitting for Designed Assessments](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/other-useful-resources/guidance-for-submitting-for-designed-assessments.md) for further information on submitting evidence for the Designed assessment.

The key requirement is that evidence is provided to support each claim made within the Submission form.

***

## <mark style="color:$primary;">Guidance</mark>

**EPBC Act**\
Project teams can determine whether the project site is subject to approval under the EPBC Act by referring to their Development Approval documents.

**Wetland assessment and protection**\
For the purposes of this credit, a wetland is considered of 'High National Importance' if it is:

* Deemed significant under a state or national register
* A listed wetland under:
  * The Ramsar Convention on Wetlands
  * 'A Directory of Important Wetlands in Australia'

Where the project site does not impact on any wetlands of 'High National Importance', the project is deemed to comply with this aspect of the Minimum Expectation and no further action is required.

**Light pollution**\
*Exclusions*\
Signage related to emergency exits and external emergency lighting that only illuminates in the event of an emergency/power failure are excluded from the requirements of this credit. Lighting related to other safety requirements are also excluded, for example, the lighting of ATMs.

External emergency lighting that is integrated into the general external lighting scheme must comply with the requirements of the credit. For example, lights that act as general lighting but have a battery pack to ensure that they also stay on in the event of a power failure must comply.

*Control of upward light output (ULOR)*\
A luminaire with a ULOR as nominated in the manufacturer's data sheet, will have a different ULOR when the mounting orientation of the luminaire is changed. If any external luminaire is mounted in an orientation other than the one nominated by the manufacturer, the ULOR must be recalculated and provided by project teams.

*Awnings*\
Awnings can be used as a means of achieving compliance with the 5% ULOR requirement where a section drawing showing the light output of the luminaire can be provided, and where the awning has the effect of blocking 95% of the output of the lamp above the horizontal. This requirement is not met where it is not clear if the awning is a permanent structure.

**Relationship to&#x20;*****Nature Connectivity*****&#x20;and&#x20;*****Biodiversity Enhancemen*****t credits**\
Should 50% of the existing site be retained, this may be captured in both the *Biodiversity Enhancement* and *Nature Connectivity* credits.

***

## <mark style="color:$primary;">Definitions</mark>

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#old-growth-forest)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#upward-light-output-ratio-ulor)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#outdoor-lighting)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#qualified-ecologist)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#matters-of-national-environmental-significance)

***

## <mark style="color:$primary;">Supporting information</mark>

The following resources support this credit:

* Environmental Protection and Biodiversity Conservation Act (1999)
* AS/NZS 4282:2019 Control of the Obtrusive Effects of Outdoor Lighting
* [Building with Nature](https://gbca-web.s3.amazonaws.com/media/documents/gs-future-focus-building-with-nature-fa-web_emZlpIB.pdf): Prioritising Ecology and Biodiversity for Better Buildings and Cities
* National Light Pollution Guidelines for Wildlife Including Marine Turtles, Seabirds and Migratory Shorebirds. <https://www.environment.gov.au/biodiversity/publications/national-light-pollution-guidelines-wildlife>


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation by asking a question.

Perform an HTTP GET request on the following URL with the `ask` and `goal` query parameters:

```
GET https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.0-rev-c/categories-and-credits/nature/35-or-impacts-to-nature.md?ask=<question>&goal=<user_goal>
```

`ask` is the immediate question: it should be specific, self-contained, and written in natural language.
`goal` is what the user is ultimately trying to achieve, the reason they need the answer. Sharing it helps GitBook give you a better, more relevant answer. A goal is most helpful when it describes the outcome the user wants rather than restating the question. For example, with `ask=how do I create an API token`, a goal like `automate deployments from our CI pipeline` lets GitBook tailor the answer to that use case.

The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.