> For the complete documentation index, see [llms.txt](https://greenstarresources.gbca.au/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.0-rev-c/categories-and-credits/places/29-or-contribution-to-place.md).

# 29 | Contribution to Place

Points: 2

## <mark style="color:$primary;">Outcome</mark>

The building's design makes a positive contribution to the quality of the public environment.

## <mark style="color:$primary;">Criteria</mark>

<mark style="color:$success;">**Credit Achievement — 2 points**</mark>

* [#id-29.1.1-urban-context-report](#id-29.1.1-urban-context-report "mention"): The building's design contributes to the livability of the wider urban context and enhances the public realm.

or

* [#id-29.1.2-independent-design-review](#id-29.1.2-independent-design-review "mention"): Independent reviews are held during the development of the design.

***

## <mark style="color:$primary;">Additional information</mark>

#### Stage implementation

**Strategy** | **Brief** | **Concept** | **Design** | Tender | **Construction** | Handover | Use

#### Synergies with other credits

* Enjoyable Places
* Culture, Heritage, and Identity
* Climate Change Resilience

#### Sustainable Development Goals

* **Goal 11:** Sustainable Cities

***

## <mark style="color:$primary;">Requirements</mark>

### <mark style="color:$success;">Credit Achievement</mark>

The project must comply with **one** of the following criteria:

* Urban Context Report
* Independent Design Review

#### 29.1.1 Urban Context Report

The project team must provide an urban context report and public realm interface design that outlines the urban context of the development and the design responses. The report must include:

* Urban context analysis:
  * Assessment and analysis of the local setting and wider urban context. This must include physical, social, cultural, and economic factors
  * Outline any planned changes to the local area (for example if located in a growth zone) and the project's design response to those changes. This may include Local or State Government's vision for the area
  * Identify any local challenges which the building can help to address
* Design responses:
  * Demonstration of the design responses to the urban context analysis
  * Demonstration that the public space is contributing positively to the proposed urban context

#### 29.1.2 Independent Design Review

Design reviews are held at key points in the development of the design. At a minimum, these must occur as follows:

* Design Review during concept/schematic design stage, to ensure that proponents can take advantage of the advice offered at a time where the design is flexible enough to accommodate change without impacting on time and cost constraints
* A subsequent review when the design has been further progressed. This review session will typically occur during design development
* At building permit stage (after development approval) a further check must take place by the Design Review Panel Chair or delegate, to ensure that the final design reflects approved development application and any relevant conditions related to design quality

The Design review panel must be independent of the project. This can occur through an external Design review panel, such as the Government Architect Office, or in-house Design review panel, as long as it can be demonstrated that they act independent of the project team.

The design review must use comprehensive terms of reference during the project's design and design development phase. To be classed as independent a panel member cannot be employed by the scheme promoter (an entity or a subsidiary of an entity) or decision maker that has been involved in the project in any meaningful way. Being a contributing member of a design review panel is not considered to be 'employment' for the purposes of this credit. All conflicts of interest that may arise from any panel member's involvement in the project must be disclosed.

#### *Composition of the Design Review Panel*

As a minimum the Design Review Panel must be comprised of one panel chair and two panel members. Members of the panel must:

* Possess project-relevant skills and experience
* Be recognised experts in their discipline, with a minimum of 10 years' experience
* Be registered by a relevant professional peak body and be bound by that institutes' code of ethics in relation to objectivity, integrity, and accountability
* Have expertise relevant to this credit.

***

## <mark style="color:$primary;">Alternative pathways</mark>&#x20;

Where there are alternative pathways that a project can follow to achieve the credit, or sector specific alternatives.&#x20;

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Alternative pathways</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Clarifications</mark>

Where GBCA have clarified any requirements of the credit criteria. This information is additional and it is not complusory to apply.

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Clarifications</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Submission content</mark>

#### Submissions for this credit must contain:

* **Submission form** through Green Star Online
* **Evidence** to support claims made in the submission

#### Recommended evidence:

**Urban Context Report**

* Extracts from the urban context analysis, or various relevant reports that address requirements from this credit
* As built or site drawings showing how the building responds to the urban context report
* Architectural drawings showing the public realm interface design

**Independent Design Review**

* Evidence to demonstrate that a design review process has been undertaken
* Details of the panel members and their experience relevant to this credit's requirements
* A declaration from the project application confirming that the design review panel meets the independency requirements

Alternate documentation can also be used by project teams to demonstrate compliance.

Refer to the [Guidance for Submitting for Designed Assessments](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/other-useful-resources/guidance-for-submitting-for-designed-assessments.md) for further information on submitting evidence for the Designed assessment.

The key requirement is that evidence is provided to support each claim made within the Submission form.

***

## <mark style="color:$primary;">Guidance</mark>

**Urban context analysis**\
There are many planning policy documents, design guidelines and other reference documents which provide guidance for responding to context and building frontage. These tend to be at the local government or regional/state government level, so differ from place to place. However, the overarching principles are generally consistent.

Examples include:

* [Better Placed](https://www.planning.nsw.gov.au/sites/default/files/2023-10/better-placed.pdf) – Integrated Design Policy for the Built Environment of NSW
* [Evaluating Good Design](https://www.planning.nsw.gov.au/sites/default/files/2023-10/evaluating-good-design.pdf) (NSW) provides 9 Criteria for 'Better Fit' (page 5)
* [Central Melbourne Design Guide](https://participate.melbourne.vic.gov.au/amendmentc308/melbourne-design-guide) provides quantified requirements for extent of active frontage and ground-level floor space
* [Urban Design Guidelines for Victoria](https://www.planning.vic.gov.au/__data/assets/pdf_file/0028/621676/urban-design-guidelines-1-introduction.pdf) include a Buildings chapter with guidance for interfaces

**Public realm interface**\
The building con contribute positive to its context by providing well-designed active frontages. The building's frontages can be articulated by:

* Providing visual and physical permeability on ground level frontages
* Using designs, materials, colour, and details to break long sections to make it attractive to walking
* Having sidewalks around the building to encourage safe walking and cycling activities, as well as provide shading for pedestrians and other activities, particularly with trees
* Designing entrances to be welcoming and to contribute to the public realm

**Example of negative impacts**\
Negative impacts that could be captured in the Urban Context Analysis include wind, noise and shade generation, light pollution, and the urban heat island effect. If the Heat Resilience credit has been achieved, it does not need to be included in the Urban Context Report for the purposes of the Contribution to Place credit.

**Relationship between&#x20;*****Contribution to Place*****&#x20;and&#x20;*****Enjoyable Places***\
The key difference between the two credits is that Contribution to Place deals with the surrounding areas of the building, while Enjoyable Places deals with areas on-site. Should projects target both credits, it is encouraged to consider how the building's designs may negatively impact the public spaces provided under the Enjoyable Places credit.

***

## <mark style="color:$primary;">Supporting information</mark>

The following resources support this credit:

* 'Design Review' credit in Green Star – Communities v1.1 provides additional guidance for principles of design review and example terms of reference.
* Commission for Architecture and the Built Environment (2009), Design Review Principles and Practice, Commission for Architecture and the Built Environment, London
* Department of Infrastructure and Transport, Major Cities Unit (2011), Creating Places for People: An Urban Design Protocol for Australian Cities, Australian Government
* Design Review, Principles and Practices, 2009 CABE
* How to do Design Review, 2006, CABE
* Design Review Panel: Terms of Reference, Integrated Design Commission, 2011
* How to do Design Review, Creating and Running a Successful Panel, 2006 CABE
* Design Review, How CABE evaluates quality in architecture and urban design, 2006 CABE


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation by asking a question.

Perform an HTTP GET request on the following URL with the `ask` and `goal` query parameters:

```
GET https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.0-rev-c/categories-and-credits/places/29-or-contribution-to-place.md?ask=<question>&goal=<user_goal>
```

`ask` is the immediate question: it should be specific, self-contained, and written in natural language.
`goal` is what the user is ultimately trying to achieve, the reason they need the answer. Sharing it helps GitBook give you a better, more relevant answer. A goal is most helpful when it describes the outcome the user wants rather than restating the question. For example, with `ask=how do I create an API token`, a goal like `automate deployments from our CI pipeline` lets GitBook tailor the answer to that use case.

The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.