> For the complete documentation index, see [llms.txt](https://greenstarresources.gbca.au/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.0-rev-c/categories-and-credits/resilient/17-or-operations-resilience.md).

# 17 | Operations Resilience

## <mark style="color:$primary;">Outcome</mark>

The building can respond to acute shocks and chronic stresses that can affect its operations over time.

## <mark style="color:$primary;">Criteria</mark>

<mark style="color:$success;">**Credit Achievement — 2 points**</mark>

* [#id-17.1.1-comprehensive-risk-assessment](#id-17.1.1-comprehensive-risk-assessment "mention"): The project team undertakes a comprehensive review of the acute shocks and chronic stresses likely to influence future building operations.
* [#id-17.1.2-managing-risks](#id-17.1.2-managing-risks "mention"): The building's design and future operational plan addresses any high or extreme system-level interdependency risks.
* [#id-17.1.3-addressing-power-loss](#id-17.1.3-addressing-power-loss "mention"): The building's design maintains a level of survivability and design purpose in a blackout.

***

## <mark style="color:$primary;">Additional information</mark>

#### Stage implementation

**Strategy** | **Brief** | **Concept** | **Design** | Tender | Construction | **Handover** | **Use**

#### Synergies with other credits

* Verification and Handover
* Climate Change Resilience
* Grid Resilience
* Community Resilience
* Energy Use
* Water Use

#### Sustainable Development Goals

* **Goal 11:** Sustainable Cities

#### Relevant reporting initiatives

* GRESB
* Task Force on Climate-related Financial Disclosures **(TCFD)**

***

## <mark style="color:$primary;">Requirements</mark>

### <mark style="color:$success;">Credit Achievement</mark>

The project must comply with **all three** of the following criteria:

* Comprehensive Risk Assessment
* Managing Risks
* Addressing Power Loss

#### 17.1.1 Comprehensive Risk Assessment

The suitably qualified professional authoring the operations resilience assessment must:

* Identify a set of clear resilience objectives and performance goals for the building
* Collaborate with key internal and external project stakeholders, including community representatives, to identify and confirm the relevant acute shocks and chronic stresses likely to impact the functionality of the building and its ability to meet performance goals
* Identify and confirm the interdependent infrastructure systems, networks, services, and assets the building relies on
* Identify key areas of system vulnerability, specifically how these may be affected by the identified shocks and stresses that may impact the building through reduced capacity and/or functionality
* Outline response procedures in the event of an identified shock event impacting the building and the local community
* Consult with relevant authorities with regards to evacuation procedures and emergency actions

As a minimum, the following shocks and stresses must be addressed in the assessment:

#### *Shocks*

* Failure of critical infrastructure (power, water and digital)
* Health pandemic
* Water security
* Geological hazards (landslides, earthquakes, tsunamis)
* Direct attack (cyber and physical)

#### *Stresses*

* Ageing infrastructure
* Rising cyber dependency
* Increasing energy costs
* Lack of transport accessibility and availability

#### 17.1.2 Managing Risks

The project team must ensure risks are addressed as follows:

* All risks rated as 'Extreme' must be addressed through specific design responses
* All risks rated as 'High' must be addressed through design or future operational responses
* Regardless of risk rating, at least two risks identified in the assessment must be addressed by specific design responses

#### 17.1.3 Addressing Power Loss

The project team must perform an assessment of the building's survivability in the case of a blackout. The building must then be designed to account for its design purpose and provide a measure of survivability for the likely occupants.

The project team must identify:

* The design purpose of the building, and the potential for the building to be occupied in the case of a blackout.
* The needs of occupants in such a situation. This may include the building being used by the community as refuge in the case of a blackout.
* The servicing needs of that building to ensure the occupants are safe during the blackout.
* The appropriate duration that the building can maintain its design purpose during the blackout.
* How the building can remain safely habitable after a blackout (specifically fire systems, ventilation, temperature, water pumping and vertical transportation).
* How the building will be able to operate in island mode, with consideration to loss of internet services for the Building Management System or for situations where the building is being powered on-site.

The building's design must account for these issues. The range of measures that can be used to address these problems can be active (through on-site generation) or passive (such as increased thermal mass to manage temperature).

***

## <mark style="color:$primary;">Alternative pathways</mark>&#x20;

Where there are alternative pathways that a project can follow to achieve the credit, or sector specific alternatives.&#x20;

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Alternative pathways</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Clarifications</mark>

Where GBCA have clarified any requirements of the credit criteria. This information is additional and it is not complusory to apply.

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Clarifications</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Submission content</mark>

#### Submissions for this credit must contain:

* **Submission form** through Green Star Online
* **Evidence** to support claims made in the submission

#### Recommended evidence:

* Operations resilience assessment
* Details of how shocks and stresses have been assessed
* Risk assessment criteria, including the likelihood and consequence tables, and any assumptions significant in the development of the assessment
* Details of the adaptation responses
* Assessment of the building's survivability during a blackout with design responses

Alternate documentation can also be used by project teams to demonstrate compliance.

Refer to the [Guidance for Submitting for Designed Assessments](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/other-useful-resources/guidance-for-submitting-for-designed-assessments.md) for further information on submitting evidence for the Designed assessment.

The key requirement is that evidence is provided to support each claim made within the Submission form.

***

## <mark style="color:$primary;">Guidance</mark>

**Staging**\
The Operations Resilience risk assessment should be completed as early during the project's design phase as possible, such as in the concept or schematic design phase, to allow maximum benefit and opportunity to inform design decisions and implement appropriate and meaningful responses.

**Climate Change Resilience**\
There is a strong link between this credit and the Climate Change Resilience credit, and it is encouraged that these are done in parallel, ideally within the same risk assessment.

If the Climate Change Resilience credit has been completed, the climate-related shocks and stresses addressed in the credit do not need to be repeated for this credit. However, if the Climate Change Resilience credit has not been completed, climate-related shocks and stresses will form part of the assessment for this credit, with appropriate physical and non-physical responses identified. Refer to the Climate Change Resilience credit for examples of climate-related shocks and stresses.

**Project scope**\
For the Operations Resilience credit, the relationship between the base building and tenanted spaces may be affected where a tenant is particularly impacted by a shock or stress that is not otherwise identified or prioritised by the building.

The project should consider where such a scenario may occur and identify potential risks to the core function of the building, or building's ability to cater to the needs of the tenant where extraordinary conditions exist. For example, if a tenant requires uninterrupted power supply, the building will need to consider if an appropriate response can be formulated to meet this requirement, and how this will affect the core function of the building. Outcomes should be communicated to tenants.

***

## <mark style="color:$primary;">Definitions</mark>

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#shocks)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#stressors)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#assessment)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#suitably-qualified-professional)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#responsible-systems)

***

## <mark style="color:$primary;">Supporting information</mark>

The following resources support this credit:

* Climate Change Resilience credit
* Australian and New Zealand Standard AS/NZ ISO 31000:2009 Risk Management


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation by asking a question.

Perform an HTTP GET request on the following URL with the `ask` and `goal` query parameters:

```
GET https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.0-rev-c/categories-and-credits/resilient/17-or-operations-resilience.md?ask=<question>&goal=<user_goal>
```

`ask` is the immediate question: it should be specific, self-contained, and written in natural language.
`goal` is what the user is ultimately trying to achieve, the reason they need the answer. Sharing it helps GitBook give you a better, more relevant answer. A goal is most helpful when it describes the outcome the user wants rather than restating the question. For example, with `ask=how do I create an API token`, a goal like `automate deployments from our CI pipeline` lets GitBook tailor the answer to that use case.

The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.