> For the complete documentation index, see [llms.txt](https://greenstarresources.gbca.au/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.0-rev-c/categories-and-credits/resilient/20-or-grid-resilience.md).

# 20 | Grid Resilience

## <mark style="color:$primary;">Outcome</mark>

The building contributes to the functioning of the grid as it transitions to a higher level of renewable energy capacity.

## <mark style="color:$primary;">Criteria</mark>

<mark style="color:$success;">**Credit Achievement — 3 points**</mark>

* [#id-20.1.1-active-generation-and-storage-systems](#id-20.1.1-active-generation-and-storage-systems "mention"): The building provides active generation and storage systems.&#x20;

and/or

* [#id-20.1.2-demand-response](#id-20.1.2-demand-response "mention"): The building has the infrastructure to deliver an appropriate demand response strategy.&#x20;

and/or

* [#id-20.1.3-passive-design-solutions](#id-20.1.3-passive-design-solutions "mention"): The building has reduced its electricity consumption through passive design.

***

## <mark style="color:$primary;">Additional information</mark>

#### Stage implementation

**Strategy** | **Brief** | **Concept** | **Design** | Tender | Construction | **Handover** | **Use**

#### Synergies with other credits

* Energy Use
* Energy Source
* Climate Change Resilience
* Operations Resilience

#### Sustainable Development Goals

* **Goal 7:** Affordable and Clean Energy
* **Goal 13:** Climate Action

#### Relevant reporting initiatives

* GRESB
* Task Force on Climate-related Financial Disclosures **(TCFD)**

***

## <mark style="color:$primary;">Requirements</mark>

### <mark style="color:$success;">Credit Achievement</mark>

The project must comply with **at least one** of the following criteria:

* Active Generation and Storage Systems
* Demand Response
* Passive Design Solutions

Project teams may provide a solution where Active Generation and Storage Systems is used with Demand Response Management. In this situation, the overall reduction must be 10% of the building's total electrical load.

#### 20.1.1 Active Generation and Storage Systems

The building has the capacity to reduce its electricity peak demand by 10% of the building's annual peak electricity demand for at least a one-hour period.

The peak demand reduction can occur through thermal storage solutions (such as chilled water storage systems), by electricity storage solutions (batteries), or through renewable on-site generation.

Where the electricity demand reduction is achieved by using on-site generation or electricity storage:

* The system (generation or storage) must incorporate switch gear and transfer switches to enable it to operate in the event of grid outage or grid demand response event. This means that the system should be able to work in either:
  * A long-term paralleling with the grid mode, such that the generator can export back to the grid
  * Island mode to power the building, or to power critical building systems
* The building must have approvals in place with the electricity utility company to operate as a peak reduction system and to have the capacity to become part of a network load demand system or to operate in island mode should it be required.

Unless a separate agreement exists with the network operator, the generator must not export more than 30% of electricity generated to the grid during peak solar generation periods. That is, the building should be consuming, storing, or transferring through a micro-grid to other buildings, most of the available excess electricity being generated.

For this pathway, the building management system (BMS) must include a demand management dashboard that shows the peak demand target, current, historical demand, alongside the critical performance characteristics. The BMS must also have the capacity to accept external control signals to enable signing up to current or future demand response programs.

The active demand management strategies must also be tested and commissioned prior to occupancy, assuming a full load profile on a peak day.

#### 20.1.2 Demand Response

The demand response strategy must show how at least 10% of the building's annual peak electricity demand is being shed without affecting occupant amenity (comfort, lighting, movement) as outlined in credits *Light Quality and Amenity and Comfort* for at least 4 hours.

This pathway relies on the building having the plan and infrastructure to manage demand responses, which includes:

* Ensuring the building's automated management system has forward predictive capabilities (based on potential weather events outside standard design days, or predictions by the network operator) to alert building management to a potential event
* Having a demand management dashboard that shows the peak demand target, current, historical demand, the demand shedding priorities and enabling button alongside the critical performance characteristics (usually comfort temperature)
* Having the building management system provide an automated way to start their load shedding strategy and enable communication to relevant parties
* Having the ability for the building's automated management system to accept external control signals to enable signing up to current or future demand response programs

This pathway also relies on ensuring the demand response strategy is tested, and that occupants and the building management system are aware what the implications are. This means:

* Including load shedding responses in the scope of work for the commissioning activities
* Including the load shedding strategy in the relevant building management manuals and training
* Introducing a communication strategy to outline to occupants how they will be impacted on the day of a potential event
* Where the building is tenanted, introducing language in leasing contracts outlining the load shedding strategies and what impacts these may have on tenants

Occupant amenity is defined as maintaining a similar level of operation as when the building is not load shedding.

#### 20.1.3 Passive Design Solutions

For this criterion to be awarded, the building must achieve the below:

* The building's facade demonstrates a 10% improvement over a reference building modelled to Section J requirements of the National Construction Code 2019, or the version of the code applicable to the building's construction, whichever is later. The calculation must follow either Method 2 in the wall/glazing calculator or use a JV3 model.
* The building is mostly naturally ventilated (that is, the building has no mechanical cooling or heating for 80% of the building's occupiable area).
* The building's occupiable area is less than 3,000sqm.

Buildings that are passively designed but don't meet this criterion, should contact the GBCA for alternative paths.

This path does not apply to industrial buildings or data centres.

***

## <mark style="color:$primary;">Alternative pathways</mark>&#x20;

Where there are alternative pathways that a project can follow to achieve the credit, or sector specific alternatives.&#x20;

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Alternative pathways</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Clarifications</mark>

Where GBCA have clarified any requirements of the credit criteria. This information is additional and it is not complusory to apply.

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Clarifications</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Submission content</mark>

#### Submissions for this credit must contain:

* **Submission form** through Green Star Online
* **Evidence** to support claims made in the submission

#### Recommended evidence:

**Active Generation and Storage Systems**

* Energy model demonstrating the buildings peak energy demand
* Description of active generation or storage systems or technologies
* Overview of the buildings BMS
* Evidence of approval with utility provider or evidence that no more that 30% of generated electricity is exported

**Demand Response**

* Description of the plan or infrastructure to manage demand response
* Evidence that the system has been implemented into building commissioning processes and tested

**Passive Design Solutions**

* Energy model showing the building's façade demonstrate a 10% improvement over reference buildings
* Mechanism drawings or other showing how the building is mostly naturally ventilated
* As built drawings showing the occupiable spaces

Alternate documentation can also be used by project teams to demonstrate compliance.

Refer to the [Guidance for Submitting for Designed Assessments](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/other-useful-resources/guidance-for-submitting-for-designed-assessments.md) for further information on submitting evidence for the Designed assessment.

The key requirement is that evidence is provided to support each claim made within the Submission form.

***

## <mark style="color:$primary;">Guidance</mark>

**Applicability**\
This credit is applicable to the energy modelling of Class 2 to 9 buildings. Refer to the Energy Use calculation guide for details on how to complete the modelling calculation, including definitions.

**Issues related to this credit**\
This credit aims to address the following issues related to enabling the ongoing transformation of the grid. The credit aims to encourage two approaches to this interaction:

* Managing demand
* Managing a building's capabilities to provide energy to the grid, or to adjust the building's demand in response to the needs of the grid at a point in time

There are five key components to this credit:

* The degree to how much the building is impacting on the grid during peak times or similar shocks
* The capacity for the building to contribute to increasing the amount of renewable energy into the grid
* The opportunity for the building to provide short or on-demand flexibility to manage its energy consumption
* Aligning supply of unscheduled generation (wind, solar) and demand for energy
* The opportunity for the building to increase the grid's resilience during its peak

If alternative solutions exist that address two or more of these components, project teams are encouraged to contact GBCA to develop an alternative path.

**Peak demand reduction**\
Project teams are encouraged to review demand response, load shifting and onsite energy storage solutions to meet this credit. Energy storage solutions may be electricity storage (for example, batteries) or thermal storage (for example, chilled water tanks).

The term "electricity demand reduction" has been referenced in this credit. Other terms, such as "peak lopping" or "peak shaving" are used interchangeably with "electricity demand reduction" and essentially deliver the same outcome.

**Onsite energy generation**\
This element of the credit aims to optimise energy generation onsite with the demand profile, either through demand response, sizing of renewables or using onsite energy storage solutions such as batteries. The purpose is not to unnecessarily reduce renewable energy generation. The intent is to encourage the availability of renewable energy at times of peak demand.

The 30% energy export has been calculated to allow for weekend energy export assuming there is no energy used onsite during that same period.

**Micro-grids**\
As the aim of this credit is for the building to work with the wider grid, a building connected to a micro-grid can use the flexibility and capacity of the micro-grid to optimise the building's impact on the wider grid.

The inclusion of micro-grids recognises precinct scale energy masterplans where some buildings have significantly higher renewable energy generation potential than it can use, such as industrial buildings. This allows buildings to export locally in a micro-grid that is designed to support the volume of energy trading, without impacting the wider electricity network.

**Onsite diesel generation and climate positive**\
This credit does not recognise the use of diesel generators to encourage managing grid interactions.

While diesel generators may be an effective way to manage grid interactions, this credit is aiming to provide a best practice approach to delivering its outcome. As diesel generators are typically found in buildings, this outcome is not considered beyond standard practice.

However, noting that diesel generators can be used to achieve the goals of this credit, we recommend scheduling the regular generator start up and loading as part of the maintenance schedules to coincide with peak demand reduction events to get maximum use of the burnt fuel. We also recommend that you review the content of this credit and consider how your generator can support grid decarbonisation. However, this will not be rewarded.

**Base building vs tenancy**\
For the *Grid Resilience* credit, the base building should consider the relationship with the tenanted spaces and how tenant operations may have an impact on the base building peak demand, both in terms of magnitude and timing.

However, we note the credit is only going to be scored on managing base building services.

In cases where tenancy or process loads were included in the peak energy calculations, the project team should detail in their submission that this is the case and note that the profile of the building shown for this credit may differ from that shown in the *Energy Use* credit.

**Future opportunities**\
While this credit is concerned at this time with the resilience of the grid during specific events, there is the opportunity to develop solutions that assist the grid on an on-going basis. This could take shape of hosting significant battery or thermal storage to help modulate grid interactions, or other similar solutions, particularly at the precinct level. We expect future updates to this credit to move in this direction.

***

## <mark style="color:$primary;">Definitions</mark>

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#baseload-demand)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#building-peak-demand)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#grid-maximum-demand)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#peak-solar-generation-period)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#occupant-amenity)

***

## <mark style="color:$primary;">Supporting information</mark>

The following resources support this credit:

* [Energy Use calculation guide](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.0-rev-c/calculation-guides/energy-use-calculation-guide.md)


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation by asking a question.

Perform an HTTP GET request on the following URL with the `ask` and `goal` query parameters:

```
GET https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.0-rev-c/categories-and-credits/resilient/20-or-grid-resilience.md?ask=<question>&goal=<user_goal>
```

`ask` is the immediate question: it should be specific, self-contained, and written in natural language.
`goal` is what the user is ultimately trying to achieve, the reason they need the answer. Sharing it helps GitBook give you a better, more relevant answer. A goal is most helpful when it describes the outcome the user wants rather than restating the question. For example, with `ask=how do I create an API token`, a goal like `automate deployments from our CI pipeline` lets GitBook tailor the answer to that use case.

The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.