> For the complete documentation index, see [llms.txt](https://greenstarresources.gbca.au/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.0-rev-c/categories-and-credits/responsible/5-or-responsible-procurement.md).

# 5 | Responsible Procurement

Points: 1

## <mark style="color:$primary;">Outcome</mark>

The procurement process for key products, materials, and services for the building's design and construction follows best practice environmental and social principles.

## <mark style="color:$primary;">Criteria</mark>

<mark style="color:$success;">**Credit Achievement — 1 point**</mark>

* [#id-5.1.1-risk-and-opportunity-assessment](#id-5.1.1-risk-and-opportunity-assessment "mention")**:** The building's design and construction procurement processes follow ISO 20400 Sustainable Procurement – Guidance by undertaking a risk and opportunities assessment.
* [#id-5.1.2-responsible-procurement-plan](#id-5.1.2-responsible-procurement-plan "mention")**:** A responsible procurement plan is developed to mitigate risks and implement opportunities identified in the assessment.

***

## <mark style="color:$primary;">Additional information</mark>

#### Stage implementation

**Strategy** | Brief | **Concept** | **Design** | **Tender** | **Construction** | Handover | Use

#### Synergies with other credits

* Responsible Structure
* Responsible Envelope
* Responsible Systems
* Responsible Finishes
* Procurement and Workforce Inclusion
* Inclusive Construction Practices

#### Sustainable Development Goals

* **Goal 8:** Decent Work and Economic Growth
* **Goal 10:** Reduced Inequalities
* **Goal 12:**  Responsible Consumption and Production

#### Relevant reporting initiatives

* GRESB

***

## <mark style="color:$primary;">Requirements</mark>

### <mark style="color:$success;">Credit Achievement</mark>

The project must comply with **both** of the following criteria:

* Risk and Opportunity Assessment
* Responsible Procurement Plan

#### 5.1.1 Risk and Opportunity Assessment

Prior to appointment of the Head Contractor, the project team must undertake a risk and opportunities assessment of 10 or more key items in the project's supply chain (as selected by the project team) to identify environmental, social and human health risks, and opportunities following ISO 20400 Sustainable Procurement – Guidance. The assessment must be completed by the design team with input from the building owner. At least one of each of the following three areas must be represented in the 10 items:

* Building Services
* Plant & Equipment
* Materials

The risk assessment must consider risks and opportunities further down the supply chain, such as in the extraction, manufacture, or transport of key materials. The risk and opportunity assessment must address at least the following issues:

* Human rights
* Labour practices
* The environment
* Fair operating practices
* Consumer issues
* Community involvement and development

#### 5.1.2 Responsible Procurement Plan

The project team must develop a plan for how the project will responsibly procure 10 or more key items mitigating risks and implementing opportunities identified in the Assessment following ISO 20400 Sustainable Procurement – Guidance as a guide to developing the plan.

The plan must:

* Identify the potential trade packages in which the 10 or more items would be procured
* Identify project-level environmental, social, economic objectives reflecting the risks and opportunities assessment
* Outline mitigation principles and standards
* Establish a governance process with roles and responsibilities for overseeing implementation of the procurement plan objectives
* Outline requirements for data collection and impact measurement monitoring and reporting
* Provide a framework for incentivising the achievement of the plan with relevant contractors and trades

The plan must be embedded in tender documentation for the head contractor or relevant trades. It must be implemented in partnership with relevant contractors and trades throughout construction, demonstrating data collection, monitoring, and reporting has been carried out.

***

## <mark style="color:$primary;">Alternative pathways</mark>&#x20;

Where there are alternative pathways that a project can follow to achieve the credit, or sector specific alternatives.&#x20;

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Alternative pathways</summary>

</details>

***

## <mark style="color:$primary;">Clarifications</mark>

Where GBCA have clarified any requirements of the credit criteria. This information is additional and it is not complusory to apply.

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Clarifications</summary>

</details>

***

## <mark style="color:$primary;">Submission content</mark>

#### Submissions for this credit must contain:

* **Submission form** through Green Star Online
* **Evidence** to support claims made in the submission

#### Recommended evidence:

* Extract from supply chain risk and opportunity assessment
* Responsible procurement plan
* Extracts from tender documents demonstrating principles and action plan was incorporated
* Meeting minutes or governance process documents
* Impact and data reporting undertaken through the construction process in partnership with relevant trades and contractors

Alternate documentation can also be used by project teams to demonstrate compliance.

Refer to the [Guidance for Submitting for Designed Assessments](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/other-useful-resources/guidance-for-submitting-for-designed-assessments.md) for further information on submitting evidence for the Designed assessment.

The key requirement is that evidence is provided to support each claim made within the Submission form.

***

## <mark style="color:$primary;">Guidance</mark>

**ISO 20400 Sustainable Procurement – Guidance**\
ISO 20400: Sustainable Procurement – Guidance provides guidance to organisations, independent of their activity or size, on integrating sustainability within procurement. The procurement process must include community involvement and development, consumer issues, fair operating practices, the environment, labour practices, and human rights. The standard also addresses organisational requirements at the middle management level, including the governance that should be in place, people management and training, stakeholder engagement, prioritisation, reporting and grievance processes. The last section sets out the procurement process itself, including planning, sourcing, and contract management.

It is expected that the design team, head contractor and sub-contractors follow the ISO 20400 guidelines to manage procurement risk in their supply chains to meet the requirements of this credit. It is not expected that all organisations downstream in the supply chain follow the ISO 20400 guidelines.

**Procurement scope**\
The *Responsible Procurement* credit deals specifically with the building's design and construction procurement processes. It does not deal with operational procurement decisions; however, it is encouraged that these processes also follow ISO 20400 Sustainable Procurement – Guidance.

**Design & construct contracts and other tender packages**\
Where a Head Contractor is engaged under a D\&C contract, they may complete the Responsible Procurement Plan where they can demonstrate this has been completed prior to letting contracts related to items in the Assessment and Plan.

**Responsible procurement plan**\
This can be part of an organisational plan or a stand-alone plan.

***

## <mark style="color:$primary;">Supporting information</mark>

The following resource supports this credit:

* [ISO 20400: Sustainable Procurement – Guidance](https://www.iso.org/standard/63026.html)


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation by asking a question.

Perform an HTTP GET request on the following URL with the `ask` and `goal` query parameters:

```
GET https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.0-rev-c/categories-and-credits/responsible/5-or-responsible-procurement.md?ask=<question>&goal=<user_goal>
```

`ask` is the immediate question: it should be specific, self-contained, and written in natural language.
`goal` is what the user is ultimately trying to achieve, the reason they need the answer. Sharing it helps GitBook give you a better, more relevant answer. A goal is most helpful when it describes the outcome the user wants rather than restating the question. For example, with `ask=how do I create an API token`, a goal like `automate deployments from our CI pipeline` lets GitBook tailor the answer to that use case.

The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.