> For the complete documentation index, see [llms.txt](https://greenstarresources.gbca.au/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.0-rev-c/categories-and-credits/sector-specific-credits/energy-use-industrial.md).

# Energy Use – Industrial

Points: 6

{% hint style="info" %}
**Sector Specific credit** **Applicability:** Industrial buildings leased to tenants, e.g. distribution centres, storage warehouses, manufacturing.

This sector specific pathway is available only under Green Star Buildings v1 and may be used as an alternative to the *Energy Use* credit in the Submission Guidelines. It cannot be claimed in addition to that credit.
{% endhint %}

## <mark style="color:$primary;">Outcome</mark>

The building has low energy consumption.

### <mark style="color:$primary;">Strategy</mark>

<table data-search="false"><thead><tr><th>Registration</th><th>Rating</th><th>Requirement</th></tr></thead><tbody><tr><td>Registering from 2020 onwards</td><td>4 Star</td><td>Meets the <em>Minimum Expectation</em></td></tr><tr><td>Registering from 2020 onwards</td><td>5 Star</td><td>Meets the <em>Minimum Expectation</em></td></tr><tr><td>Registering from 2020 onwards</td><td>6 Star</td><td>Meets the <em>Credit Achievement</em></td></tr><tr><td>Registering from 2023 onwards</td><td>4 Star</td><td>Meets the <em>Minimum Expectation</em></td></tr><tr><td>Registering from 2023 onwards</td><td>5 Star</td><td>Meets the <em>Credit Achievement</em></td></tr><tr><td>Registering from 2023 onwards</td><td>6 Star</td><td>Meets the <em>Credit Achievement</em></td></tr><tr><td>Registering from 2026 onwards</td><td>4 Star</td><td>Meets the <em>Credit Achievement</em></td></tr><tr><td>Registering from 2026 onwards</td><td>5 Star</td><td>Meets the <em>Credit Achievement</em></td></tr><tr><td>Registering from 2026 onwards</td><td>6 Star</td><td>Meets the <em>Credit Achievement</em></td></tr><tr><td>Certified after 1st January 2030, regardless of registration date</td><td>All certifications</td><td>Meets the <em>Credit Achievement</em></td></tr></tbody></table>

## <mark style="color:$primary;">Criteria</mark>

<mark style="color:$success;">**Minimum Expectation — Nil**</mark>

* **Minimum Energy Efficiency:** The building meets minimum prescriptive energy efficiency requirements

<mark style="color:$success;">**Credit Achievement — 3 points**</mark>

– Climate Positive Pathway –

In addition to the *Minimum Expectation*

* **Energy Efficiency Measures:** The building has several energy efficiency attributes or onsite renewables.

<mark style="color:$success;">**Exceptional Performance — 3 points**</mark>

In addition to the *Credit Achievement*

* The building has higher number of energy efficiency attributes and/or higher onsite renewables.

***

## <mark style="color:$primary;">Additional information</mark>

#### **Stage implemented**

**Strategy** | **Brief** | **Concept** | **Design** | **Tender** | **Construction** | Handover | Use

#### **Synergies with other credits**

* Verification and Handover
* Life Cycle Impacts
* Climate Change Resilience
* Operations Resilience
* Grid Resilience

#### **Sustainable Development Goals**

* **Goal 7:** Affordable and Clean Energy
* **Goal 13:** Climate Action

#### **Relevant reporting initiatives**

* GRESB
* Task Force on Climate-related Financial Disclosures **(TCFD)**

***

## <mark style="color:$primary;">Requirements</mark>

### <mark style="color:$success;">Minimum Expectation</mark>

The project must comply with the following criteria:

* Minimum Energy Efficiency

#### **Minimum Energy Efficiency**

#### *Unconditioned warehouse Spaces*

The warehouse spaces within the building achieve all the following:

* a 5% improvement in the Lighting Power Density (LPD) based on the maximum allowable lighting power densities defined in NCC Section J Table J6.2a
* daylight sensors to control artificial lighting
* more than 5% of the roof area is dedicated to skylights

#### *Conditioned Office Spaces*

The conditioned office spaces within the building achieve both the following:

* a 5% improvement in the Lighting Power Density (LPD) based on the maximum allowable lighting power densities defined in NCC Section J Table J6.2a
* conditioned envelope fabric exceeds the requirements of NCC Section J Part J1

### <mark style="color:$success;">Credit Achievement</mark>

In addition to the *Minimum Expectation*, the project must comply with **one** of the following criteria:

* Energy Efficiency Measures
* Onsite Renewables

#### Energy Efficiency Measures

The building complies with any **three** of the energy efficiency measures.

<table data-search="false"><thead><tr><th width="224">Energy Efficiency measures</th><th>Requirements</th></tr></thead><tbody><tr><td>Internal artificial lighting</td><td><p>The internal artificial lighting installed in the building complies with all of the following:</p><p></p><p>• The average installed aggregate illumination power is not more than 80% of the maximum illumination power based on the maximum allowable lighting power densities defined in NCC Section J Table J6.2a.</p><p></p><p>• Automated lighting control systems, such as occupant detection and daylight adjustment, are provided to 95% of the gross lettable warehouse area.</p><p></p><p>• For Class 5 components only, the size of individually switched lighting zones does not exceed 150 m² for 95% of the office area.</p></td></tr><tr><td>External artificial lighting</td><td><p>The external artificial lighting installed in the building complies with all of the following:</p><p></p><p>• All external lighting must be weatherproof, impact resistant and meet the control requirements of NCC Section J Part J6.5, b and comply with the <em>Impacts to Nature</em> Credit.</p><p></p><p>• All lighting to external loading docks with awnings must be a maximum 4W/m² illumination power density.</p></td></tr><tr><td>Building Envelope</td><td><p>The installed roofs and ceilings in the project, floors and roof lights in all conditioned spaces comply with all of the following:</p><p></p><p>• The project achieves a 10% increase on the minimum required total R-values specified for roofs and ceilings in Part J1.3, and floors in Part J1.6, including compliance with J0.4 where applicable</p><p></p><p>• Roofs have an upper surface solar absorptance of at least 0.05 less than the maximum allowable value in Part J1.3</p><p></p><p>• Roof lights achieve a total system U-value of less than or equal to 3.3 W/m².K</p><p></p><p>• Roof lights achieve a total system SHGC of less than or equal to 85% of the maximum allowable value in Part J1.4</p></td></tr><tr><td>Wall Glazing and Construction</td><td><p>The wall-glazing constructions and retail display glazing installed in the building comply with all of the following:</p><p></p><p>• Wall-glazing constructions achieve an area-weighted total system U-value, across all facades (Specification J1.5a U-Value – Method 2), at least 10% less than the maximum allowable total system U-value for wall-glazing constructions as per the requirements of Part J1.5, including compliance with Part J0.5 where applicable</p><p></p><p>• Wall-glazing constructions have a combination of solar heat gain coefficients, across all facades (Specification J1.5a Solar admittance – Method 2), that achieve a calculated proposed representative air-conditioning energy value of not more than 90% of the calculated reference representative air-conditioning energy value as per the requirements of Part J1.5</p><p></p><p>• Where the wall component is 80% or more of the area of the wall-glazing construction, it achieves a 10% increase on the minimum total R-value specified in Table J1.5a</p></td></tr><tr><td>Domestic Hot Water</td><td><p>The domestic hot water systems are powered by one of the following heat sources:</p><p></p><p>• Electric heat pump with annual energy savings greater than 60% measured in accordance with AS/NZS 4234.</p><p></p><p>• Electric boilers with solar PV installed on site</p><p></p><p>• Waste heat or heat recovered from another process.</p></td></tr><tr><td>Ventilation and Air Conditioning</td><td><p>All installed HVAC equipment complies with all the following:</p><p></p><p>• Each installed fan must achieve a fan motor input power per unit of flow rate 15% lower than the reference fan motor input power per unit flow rate calculated from the deemed-to-satisfy requirements of Part J5.4 (b), (c), (d) and (e).</p><p></p><p>• Each installed pump must achieve a pump motor input power per unit of flow rate 10% lower than the reference pump motor input power per unit flow rate calculated from the deemed-to-satisfy requirements of Part J5.7 (b), (c) and (d).</p><p></p><p>• The thermal efficiency of all installed electric water heaters is at least 4 percentage points more than the minimum value required by Part J5.9(d)</p><p></p><p>• The minimum energy efficiency ratio (EER) (cooling) for all unitary air conditioning equipment is at least 5% higher than the required minimum EER (cooling) as per Part J5.11.</p><p></p><p>• The minimum energy efficiency ratio (EER) and integrated part-load value (IPLV) for all refrigerant chillers are at least 15% higher than the minimum values specified in Table J5.10a/b for the relevant chiller type and capacity.</p><p></p><p>Naturally ventilated spaces (including naturally ventilated mode of mixed-mode systems and regularly occupied unconditioned warehouse space) complies with the requirements of Clean Air credit</p><p></p><p>Where HVAC is only provided to office component of the building, the HVAC complies with all of the following:</p><p></p><p>• The minimum Energy Rating Labelling for unitary air-conditioning equipment must be at least 4-star as per AS/NZS 3823.2:2013</p><p></p><p>• The rated cooling or heating capacity of the unit does not exceed the design cooling or heating load, whichever is greater, by more than 15%.</p></td></tr><tr><td>On-site Storage</td><td><p>There are on-site storage systems present that comply with the following:</p><p></p><p>• A renewable energy storage procurement and use strategy has been developed and demonstrates that the storage system installed is match's the requirements of the building and that value will be provided to the building</p><p></p><p>• The stored renewable energy is used to reduce the peak electricity demand</p><p></p><p>• A building installs and uses electricity storage such that on-site renewable energy not instantaneously used by the building is able to be stored and used by the building later</p></td></tr></tbody></table>

#### **Onsite Renewables**

#### *Onsite Solar PV Installation*

At least 99 kW of Solar PV per 10,000m² of Gross Lettable Area (GLA) is installed on-site.

The PV is to be installed such that it is oriented in a direction that allows the maximum output and not overshadowed.

#### *Onsite PV Consumption*

The PV is connected to the building (behind the meter) and contributes to the energy use of the building before any excess is exported or sold.

### <mark style="color:$success;">Exceptional Performance</mark>

The building complies with **one** of the following criteria:

* Energy Efficiency Measures and Onsite renewables
* High Energy Efficiency Measures
* High Onsite Renewables

#### **Energy Efficiency Measures and Onsite Renewables**

The building complies with **both** of following criteria

* Energy Efficiency Measures
* Onsite Renewables

Refer to *Credit Achievement* for requirements

#### **High Energy Efficiency Measures**

The building complies with at least six of the seven the energy efficiency measures available.

* Energy Efficiency Measures

Refer to Credit Achievement for requirements

#### **High Onsite Renewables**

#### *Onsite PV Installation*

At least 198 kW of Solar PV per 10,000m² of Gross Lettable Area (GLA) is installed on-site.

The PV is to be installed such that it is oriented in a direction that allows the maximum output and not overshadowed.

#### *Onsite PV Consumption*&#x20;

The PV is connected to the building (behind the meter) and contributes to the energy use of the building before any excess is exported or sold.

***

## <mark style="color:$primary;">Submission content</mark>

#### Submissions for this credit must contain:

* **Submission form** through Green Star Online
* **Evidence** to support claims made in the submission

#### **Recommended evidence:**

* Extracts from specifications
* Extracts from commissioning reports
* As built drawings of the façade
* Evidence of renewable energy generation on-site (e.g., contracts, as built drawings)

Alternate documentation can also be used by project teams to demonstrate compliance.

The recommended evidence listed above is applicable to the as built submission. See the Design assessment documentation section in the Introduction for more information on submitting evidence for the Design assessment.

The key requirement is that evidence is provided to support each claim made within the Submission form.

***

## <mark style="color:$primary;">Guidance</mark>

Guidance is supporting information for the credit requirements and is not mandatory to apply.

**R-values and U-values (Conditioned envelope fabric)**\
R-values and U-values for building fabric and glazing must be for the full façade or glazing panel and take into account thermal bridging. U-values for glazing must be for the full glazing system, including framing, determined in accordance with Australian Fenestration Rating Council methods. Centre panel/pane values are not acceptable.

**Solar heat gain/solar shading coefficients (glazing)**\
Solar heat gain and solar shading coefficients must be for the full glazing system, including framing, determined in accordance with Australian Fenestration Rating Council methods. Centre pane values are not acceptable.

**AS/NZS 4234 - Heated water systems - Calculation of energy consumption**\
The AS/NZS 4234 standard has been designed to provide a means of evaluating the annual task performance of heated water systems.

Products eligible for Victorian Energy Efficiency Certificates (VEEC) under the Victorian Energy Upgrades (VEU) program for heat pump water heaters under zone 4 and zone 5 are deemed to comply with the requirements of the credit.

**Victorian Energy Upgrades (VEU) program**\
The Victorian Energy Upgrades (VEU) program helps Victorians reduce their energy bills and greenhouse gas emissions by providing access to discounted energy efficient product and services. The program also encourages investment, employment and innovation in industries that supply these products and services.

Heat Pumps and Solar Electric boosted hot water systems recognised under the VEU program can be found here: <https://www.veu-registry.vic.gov.au/Public/ProductRegistrySearch.aspx>

**Victorian Energy Efficiency Certificates (VEECs)**\
Victorian energy efficiency certificates (VEECs) are electronic certificates created under the VEU program when certain energy efficiency activities are undertaken in residential or non-residential premises.

For the purposes of this credit, projects in other states may use these certificates to demonstrate compliance with this credit.

***

## <mark style="color:$primary;">Supporting information</mark>

The following resources support this credit:

* Australian Building Codes Board (ABCB), National Construction Code 2019 Volume One, Australian Building Codes Board, Australia
* GBCA's Climate positive buildings and our net zero ambitions
* GBCA's Climate Positive Roadmap


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation by asking a question.

Perform an HTTP GET request on the following URL with the `ask` and `goal` query parameters:

```
GET https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.0-rev-c/categories-and-credits/sector-specific-credits/energy-use-industrial.md?ask=<question>&goal=<user_goal>
```

`ask` is the immediate question: it should be specific, self-contained, and written in natural language.
`goal` is what the user is ultimately trying to achieve, the reason they need the answer. Sharing it helps GitBook give you a better, more relevant answer. A goal is most helpful when it describes the outcome the user wants rather than restating the question. For example, with `ask=how do I create an API token`, a goal like `automate deployments from our CI pipeline` lets GitBook tailor the answer to that use case.

The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.