> For the complete documentation index, see [llms.txt](https://greenstarresources.gbca.au/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.1/categories-and-credits/nature-2/41-or-nature-stewardship.md).

# 41 | Nature Stewardship

Points: 2

## <mark style="color:$primary;">Outcome</mark>

Biodiversity is restored beyond the building site.

## <mark style="color:$primary;">Criteria</mark>

<mark style="color:$success;">**Credit Achievement — 1 point**</mark>

* [#id-41.1.1-protection-and-restoration-activities](#id-41.1.1-protection-and-restoration-activities "mention"): Areas of restoration and/or protection are provided.

<mark style="color:$success;">**Exceptional Performance — 1 point**</mark>

* [#id-41.2.1-increased-protection-and-restoration-activities](#id-41.2.1-increased-protection-and-restoration-activities "mention"): An increased area of restoration and/or protection are provided.

***

## <mark style="color:$primary;">Additional information</mark>

#### Scope of credit

Land outside the site boundary and beyond legislated/mandated requirements.

This does not include purchased biodiversity offsets or any actions required to be taken as part of an EPBC action, development approval, or other legislated requirements (including biodiversity offsets, invests in or directly actions land restoration, or similar).

#### Stage implementation

**Strategy** | **Brief** | **Concept** | **Design** | **Tender** | **Construction** | **Handover** | **Use**

#### Synergies with other credits

* Impacts to Nature

#### Sustainable Development Goals

* **Goal 15:** Life on Land

#### Relevant reporting initiatives

* GRESB
* Task Force on Nature-related Financial Disclosure **(TNFD)**

***

## <mark style="color:$primary;">Requirements</mark>

### <mark style="color:$success;">Credit Achievement</mark>

The project must comply with the following criterion:

* Restoration and Protection Activities

#### 41.1.1 Protection and Restoration Activities

The building owner undertakes activities to protect and/or restore ecosystems outside the site boundary. The area of restoration or protection is at least 50% of the total GFA of the building or at least 50% of the area within the project boundary, whichever is greater.

Project teams may choose from one or both of the following pathways:

<table><thead><tr><th width="166.5">Pathway</th><th>Requirements</th></tr></thead><tbody><tr><td><strong>Direct protection and/or restoration</strong></td><td>The building owner protects and restores the ecological values of a purchased site.<br><br>A Restoration and/or Protection Management Plan for the purchased site is prepared by a suitably qualified ecologist. The plan includes a strategy and timeframes on how the site will be protected to maintain its ecological value and/or how the site will be restored to be equivalent in ecological value to the site prior to development. This is validated by an independent qualified ecologist or a similar suitably qualified professional.<br><br>The building owner commits to set-aside and manages the site land in perpetuity including on-going funding provision.</td></tr><tr><td><strong>Supporting an organisation that restores and/or protects nature on the project's behalf</strong></td><td>The building owner establishes a partnership with a relevant organisation to deliver protection, restoration or improvement and ongoing management of land on behalf of the project.<br><br>The restoration and/or protection activities are verified by an independent qualified ecologist or other suitably qualified professional.</td></tr></tbody></table>

For both pathways, the project team demonstrates land designated for restoration and protection meets the following:

* **Location of activities**: Land for restoration or protection is in Australia. The location of the land designated for the offsite restoration is not in the site boundary.
* **Verification of ecological value:** A qualified ecologist confirms that the ecological value is equivalent to the land on which the building is being developed and is restored to equivalent ecological value of the site before any developed occurred or protected.
* **Exclusivity of land use:** The land being claimed is designated exclusively to the project and not being claimed as restoration activities against any other site.
* **Additionality:** Activities go beyond any legislated requirements and demonstrate how these actions achieve outcomes that would not have occurred without the intervention.
* **Longevity:** Protection of the land is secured in perpetuity.

The above information is included in the Restoration and/or Protection Management Plan if direct protection and/or restoration is pursued.

### <mark style="color:$success;">Exceptional Performance</mark>

The project must comply with the following criterion:

* Increased Restoration and Protection Activities

#### 41.2.1 Increased Protection and Restoration Activities

The building owner undertakes activities to protect and/or restore ecosystems outside the site boundary. The area of restoration or protection is equivalent to the total GFA of the building or the area within the project boundary, whichever is greater.

Refer [*Credit Achievement*](#id-41.1.1-protection-and-restoration-activities) for pathways for activities.

***

## <mark style="color:$primary;">Alternative pathways</mark>&#x20;

Where there are alternative pathways that a project can follow to achieve the credit, or sector specific alternatives.&#x20;

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Alternative pathways</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Clarifications</mark>

Where GBCA have clarified any requirements of the credit criteria. This information is additional and it is not complusory to apply.

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Clarifications</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Definitions</mark>

Definitions provided here must be applied to Requirements unless agreed with GBCA via a Technical Question.

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#gross-floor-area-gfa)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#project-boundary)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#qualified-ecologist)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#similar-qualified-professional)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#site-boundary)

***

## <mark style="color:$primary;">Guidance</mark>

Guidance is supporting information for the credit requirements and is not mandatory to apply.

**Off-site vs. on-site restoration**\
Actions to enhance biodiversity within the site are addressed by other credits in this category.

As the aim of this project is to increase biodiversity in areas outside the site as far as practicable, solutions that enhance the site, or adjacent buildings that are owned or developed by the same entity, are unlikely to be considered for this credit. There may be exceptions, for example where the enhancement is occurring in another area of a precinct or campus (e.g., a waterway restoration activity). However, in such a situation, it would expect to see how the enhancement is tied to the rated project, how it is being funded, and how it is additional – it wouldn't have happened otherwise.

**Restoration activities**\
The range of possible offsite restoration actions may include the following:

* Habitat improvement, restoration, or expansion
* Direct threat mitigation
* Installation of artificial structures or habitats
* Ecological recycling or re-use of natural materials
* Re-introduction of species or natural processes
* Monitoring and benchmarking

**Examples of partner organisations**\
The below are some example organisations that may be used for the second pathway.

* Local Aboriginal Land Council – refer below
* Biodiversity Conservation Trust of NSW
* Bush Heritage Australia
* Greening Australia
* Landcare Australia
* Queensland Trust for Nature
* Nature Foundation SA
* South Endeavour Trust
* Tasmanian Land Conservancy
* The Nature Conservancy – Australia Program

Other organisations may be used, provided their activities are verified by a third party.

**Local land councils**\
Local Lands Councils represent the local communities and Aboriginal landowners during consultation processes of land use proposals. There are councils in each state which are a key source of information for projects based in these areas. Links are provided below as a starting point for project teams.

<table data-search="false"><thead><tr><th width="102">State</th><th width="177">Area</th><th width="481">Link</th></tr></thead><tbody><tr><td>ACT</td><td>Region</td><td><a href="https://www.ngunnawal.org/united-ngunnawal-elders-council">https://www.ngunnawal.org/united-ngunnawal-elders-council</a></td></tr><tr><td rowspan="2">QLD</td><td>North and Central</td><td><a href="https://nqlc.com.au/">https://nqlc.com.au/</a></td></tr><tr><td>Cape York</td><td><a href="http://www.cylc.org.au/">http://www.cylc.org.au/</a></td></tr><tr><td rowspan="2">NSW</td><td>Region</td><td><a href="https://alc.org.au/">https://alc.org.au/</a></td></tr><tr><td>Sydney</td><td><a href="https://metrolalc.org.au/">https://metrolalc.org.au/</a></td></tr><tr><td>VIC</td><td>Region</td><td><a href="https://bglc.com.au/">https://bglc.com.au/</a></td></tr><tr><td>SA</td><td>Region</td><td><a href="https://www.agd.sa.gov.au/aboriginal-affairs-and-reconciliation/south-australian-aboriginal-advisory-council">https://www.agd.sa.gov.au/aboriginal-affairs-and-reconciliation/south-australian-aboriginal-advisory-council</a><br><br><a href="https://alt.sa.gov.au/">https://alt.sa.gov.au/</a></td></tr><tr><td rowspan="4">WA</td><td>South-West</td><td><a href="https://www.noongar.org.au/">https://www.noongar.org.au/</a></td></tr><tr><td>Goldfields</td><td><a href="https://abcau.com.au/partners/gacs/">https://abcau.com.au/partners/gacs/</a></td></tr><tr><td>Kimberley</td><td><a href="https://www.klc.org.au/">https://www.klc.org.au/</a></td></tr><tr><td>Ngaanyatjarra</td><td><a href="https://www.ngaanyatjarra.org.au/">https://www.ngaanyatjarra.org.au/</a></td></tr><tr><td>TAS</td><td>Region</td><td><a href="https://alctas.org.au/">https://alctas.org.au/</a></td></tr><tr><td rowspan="4">NT</td><td>Central</td><td><a href="https://www.clc.org.au/">https://www.clc.org.au/</a></td></tr><tr><td>North</td><td><a href="https://www.clc.org.au/">https://www.clc.org.au/</a></td></tr><tr><td>Tiwi</td><td><a href="https://www.tiwilandcouncil.com/">https://www.tiwilandcouncil.com/</a></td></tr><tr><td>Anindilyakawa</td><td><a href="https://anindilyakwa.com.au/">https://anindilyakwa.com.au/</a></td></tr><tr><td>Torres-Strait Islands</td><td>Region</td><td><a href="https://tsirc.qld.gov.au/">https://tsirc.qld.gov.au/</a></td></tr></tbody></table>

***

## <mark style="color:$primary;">Submission content</mark>

Submissions for this credit must contain:

* **Submission form** through Green Star Online
* **Evidence** to support claims made in the submission

#### Recommended evidence

The following list of evidence serves as a guide for the Certified submission and is not exhaustive. Project teams are not required to provide all of the listed items and alternate forms of documentation can be used to demonstrate compliance. The key requirement is that evidence is provided to support each claim.

* Restoration and/or Protection Management Plan.
* Evidence of site purchase and its location.
* Evidence of formal partnership.
* Overview of restoration activities.
* Evidence of funding provisions and that the land is secured in perpetuity.
* Evidence of project specific additionality.
* Evidence of independent validation.

Refer to the [Guidance for Submitting for Designed Assessments](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/other-useful-resources/guidance-for-submitting-for-designed-assessments.md) for further information on submitting evidence for the Designed assessment.

***

## <mark style="color:$primary;">Supporting information</mark>

The following resource supports this credit:

* DCCEEW – [Investing in nature](https://www.dcceew.gov.au/environment/environmental-markets/investing-in-nature)
* GBCA – Building with Nature: Prioritising Ecology and Biodiversity for Better Buildings and Cities
* GBCA – [Nature positive roadmap](https://gbca-web.s3.amazonaws.com/media/documents/draft-nature-positive-roadmap.pdf)


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation by asking a question.

Perform an HTTP GET request on the following URL with the `ask` and `goal` query parameters:

```
GET https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.1/categories-and-credits/nature-2/41-or-nature-stewardship.md?ask=<question>&goal=<user_goal>
```

`ask` is the immediate question: it should be specific, self-contained, and written in natural language.
`goal` is what the user is ultimately trying to achieve, the reason they need the answer. Sharing it helps GitBook give you a better, more relevant answer. A goal is most helpful when it describes the outcome the user wants rather than restating the question. For example, with `ask=how do I create an API token`, a goal like `automate deployments from our CI pipeline` lets GitBook tailor the answer to that use case.

The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.