> For the complete documentation index, see [llms.txt](https://greenstarresources.gbca.au/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.1/categories-and-credits/people-3/34-or-inclusive-construction-practices.md).

# 34 | Inclusive Construction Practices

Points: 1

## <mark style="color:$primary;">Outcome</mark>

The builder's construction practices promote diversity and reduce physical and mental health impacts.

## <mark style="color:$primary;">Criteria</mark>

<mark style="color:$success;">**Minimum Expectation — Nil**</mark>

* [#id-34.0.1-facilities-and-equipment](#id-34.0.1-facilities-and-equipment "mention"): Gender inclusive facilities and protective equipment are provided on-site.
* [#id-34.0.2-policies-and-training](#id-34.0.2-policies-and-training "mention"): On-site policies are implemented to increase awareness and reduces instances of discrimination, racism and bullying.

<mark style="color:$success;">**Credit Achievement — 1 point**</mark>

In addition to *Minimum Expectation:*

* [#id-34.1.1-physical-and-mental-health-programs](#id-34.1.1-physical-and-mental-health-programs "mention"): Programs are provided to on-site workers.
* [#id-34.1.2-program-evaluation](#id-34.1.2-program-evaluation "mention"): The programs delivered are evaluated.

***

## <mark style="color:$primary;">Additional information</mark>

#### Scope of credit

Workers on site for three days or more, who are contracted, sub-contracted or employed by the head contractor of the main works. This includes demolition and early works if included in the same contract as the main works.

#### Stage implementation

**Strategy** | **Brief** | Concept | Design | **Tender** | **Construction** | Handover | Use

#### Synergies with other credits

* Procurement and Workforce Inclusion

#### Sustainable Development Goals

* **Goal 5:** Gender Equality
* **Goal 8:** Decent Work and Economic Growth

***

## <mark style="color:$primary;">Requirements</mark>

### <mark style="color:$success;">Minimum Expectation</mark>

The project must comply with **both** of the following criteria:

* Facilities and Equipment
* Policies and Training

#### 34.0.1 Facilities and Equipment

The head contractor ensures the following is implemented on-site:

* Separate gender inclusive bathroom facilities and changing amenities, with acoustic and visual privacy between each facility.
* A policy to ensure fit-for-purpose personal protective equipment (PPE) for diverse body sizes and types are available to all workers and visitors.

The above are provided by the head contractor of the main works for the duration of all works under the contract.

#### 34.0.2 Policies and Training

The head contractor ensures the on-site leadership team are empowered to proactively implement the following:

* Policies to address issues of discrimination, racism and bullying on-site and safe ways to report related incidents.
* On-site redress procedures for any relevant breaches and corrective measures for identified incidents.
* Training on the following areas are provided to 95% of all contractors and subcontractors present on site for at least three days for:
  * Information on drug and alcohol awareness and mental health.
  * Information on policies implemented on discrimination, racism, bullying on-site, and safe ways to report poor behaviour.

### <mark style="color:$success;">Credit Achievement</mark>

In addition to *Minimum Expectation*, the project must comply with both of the following criteria:

* Physical and Mental Health Programs
* Program Evaluation

#### 34.1.1 Physical and Mental Health Programs

The head contractor has introduced programs and solutions on-site.

* For contracts valued less than $10 million, at least three areas of physical and mental health are to be addressed.
* For contracts valued at over $10 million, at least five areas of physical and mental health are to be addressed.

The programs and solutions are implemented no later than 3 months of starting construction works and are in place for the remaining duration of construction.

A mix of programs is acceptable. The programs cover at least 80% of the workforce that have attended the site for more than three days from commencement on site to practical completion. The programs or solutions can be implemented directly by the head contractor or through partnerships with mental and physical health organisations.

Refer *Guidance* for examples of physical and mental health programs.

#### 34.1.2 Program Evaluation

An evaluation report of the programs is provided to the head contractor's head office and subcontractors with the following:

* Information on the programs or initiatives that were delivered, including information on dates, attendance, and available languages.
* Feedback on the programs or initiatives from those that benefitted.
* Recommendations for improving the future delivery of programs.

***

## <mark style="color:$primary;">Alternative pathways</mark>&#x20;

Where there are alternative pathways that a project can follow to achieve the credit, or sector specific alternatives.&#x20;

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Alternative pathways</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Clarifications</mark>

Where GBCA have clarified any requirements of the credit criteria. This information is additional and it is not complusory to apply.

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Clarifications</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Definitions</mark>

Definitions provided here must be applied to Requirements unless agreed with GBCA via a Technical Question.

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#gender-inclusive)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#personal-protective-equipment)

***

## <mark style="color:$primary;">Guidance</mark>

Guidance is supporting information for the credit requirements and is not mandatory to apply.

**Gender inclusivity**\
This *Minimum Expectation* is seeking to remove physical barriers to participation in the construction workforce for different groups, particularly women who represent less than 2% of the construction and building workforce (<https://tradeswomenaus.com/>). The provision of separate male and female bathrooms and changing facilities are a minimum. This may change in future revisions of the rating tool as the industry evolves.

Should the building's construction identify opportunities to provide additional improvements beyond facilities and gender-specific PPE to celebrate diversity, they should be pursued. Where this is the case, the building may seek an additional point(s) in the *Leadership* category, under *Market Transformation*.

**Policy for fit-for-purpose PPE**\
The intent of the policy is to ensure that fit-for-purpose PPE is made available by the head contractor to reduce on-site hazards for all workers and visitors. This may be in the form of:

* PPE being provided directly by the head contractor. The PPE is available in a variety of sizes and fits.
* PPE being purchased on behalf of the site workers by the head contractor and a diverse range of gender-specific fit-for-purpose PPE is provided by the head contractor for visitors.
* Site workers are responsible for bringing their own PPE to site however education on the importance of fit-for-purpose PPE is provided by the head contractor. A diverse range of gender-specific fit-for-purpose PPE is provided by the head contractor for visitors.

Opportunities to request and be provided with better fitting PPE are also available and provided by the head contractor.

**Cultural and language barriers identified on site**\
When training and policies are developed, consideration should be given to the method and form of delivery and actions are taken to address cultural and language barriers.

**Physical and mental health programs**\
Examples of areas of physical and mental health that can be addressed include:

* Suicide prevention
* Healthy eating and active living
* Reduce harmful alcohol and tobacco consumption and avoid drug use
* Increased social cohesion, community, and cultural participation
* Understanding depression, anxiety and other mental health conditions
* Preventing violence and injury
* Decreased psychological stress and building coping mechanisms
* Finding fulfilment at work or mindful meditation
* Other issues identified by site workers

More than one area of physical and mental health can be addressed by the same program or solution.

**Program evaluation report**\
Feedback from those who benefitted from the programs may be collected by conducting a questionnaire or having conversations in small focus groups or one-on-one with the main intent being that the opinions of those that benefitted from the programs are sought. Where no responses are received, the program team is to demonstrate that considerable effort has been made to collect this information and improvements for collecting this data in future are proposed.

***

## <mark style="color:$primary;">Submission content</mark>

Submissions for this credit must contain:

* **Submission form** through Green Star Online
* **Evidence** to support claims made in the submission

#### Recommended evidence

The following list of evidence serves as a guide for the Certified submission and is not exhaustive. Project teams are not required to provide all of the listed items and alternate forms of documentation can be used to demonstrate compliance. The key requirement is that evidence is provided to support each claim.

**Facilities and Equipment**

* Evidence (e.g., photos, register or similar) of the PPE available to construction workers
* Evidence of purchase or availability of appropriate PPE
* Evidence (e.g., photos, correspondence or similar) of separate bathroom facilities and changing amenities

**Policies and Training**

* Evidence from head contractor that outlines the approach of empowering the on-site leadership team.
* Extracts from relevant policies that address discriminating, racism and bullying.
* Evidence that training has been provided on-site.
* Extracts of the training (e.g., screenshots, presentation content or similar) showing the information provided as part of training.
* Evidence of attendance and that 95% of all contractors and subcontractors on site for at least three days attended.

**Needs Analysis**

* Needs Analysis report outlining engagement process and outcomes for training.

**Physical and Mental Health Programs**

* Extracts of evidence detailing the programs implemented to promote health and wellbeing on site, including where applicable reports from third-party provider/s or similar.
* Evidence of attendance and how the programs have covered 80% of the workforce that have attended the site for more than three days from commencement on site to practical completion.

**Program Evaluation**

* Evaluation report of the training from the on-site, head contractor team including details on the programs, feedback and recommendations for future delivery.

Refer to the [Guidance for Submitting for Designed Assessments](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/other-useful-resources/guidance-for-submitting-for-designed-assessments.md) for further information on submitting evidence for the Designed assessment.

***

## <mark style="color:$primary;">Supporting information</mark>

The following resource supports this credit:

* BSI – [Diversity in Personal Protective Equipment](https://page.bsigroup.com/diversity-in-ppe)
* Construction Industry Culture Taskforce – [A Culture Standard for the Construction Industry](https://cict.mymedia.delivery/wp-content/uploads/2025/08/A-Culture-Standard-for-the-Construction-Industry_FINAL_Digital_A4.pdf)
* Construction Industry Culture Taskforce – [Wellbeing Implementation Guide and Toolkit](https://cict.mymedia.delivery/wp-content/uploads/2025/06/Wellbeing-Implementation-Guide-and-Toolkit_FINAL.pdf)
* Government of South Australia – Healthy Workplaces – [Conduct a workplace needs assessment](https://www.healthyworkplaces.sa.gov.au/step-by-step-guide/step-2-learn-about-your-workplace/conduct-a-workplace-needs-assessment)


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation by asking a question.

Perform an HTTP GET request on the following URL with the `ask` and `goal` query parameters:

```
GET https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.1/categories-and-credits/people-3/34-or-inclusive-construction-practices.md?ask=<question>&goal=<user_goal>
```

`ask` is the immediate question: it should be specific, self-contained, and written in natural language.
`goal` is what the user is ultimately trying to achieve, the reason they need the answer. Sharing it helps GitBook give you a better, more relevant answer. A goal is most helpful when it describes the outcome the user wants rather than restating the question. For example, with `ask=how do I create an API token`, a goal like `automate deployments from our CI pipeline` lets GitBook tailor the answer to that use case.

The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.