> For the complete documentation index, see [llms.txt](https://greenstarresources.gbca.au/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.1/categories-and-credits/resilient-2/17-or-climate-resilience.md).

# 17 | Climate Resilience

Points: 1

## <mark style="color:$primary;">Outcome</mark>

The building has been built to respond to the direct and indirect impacts of climate change.

## <mark style="color:$primary;">Criteria</mark>

<mark style="color:$success;">**Minimum Expectation — Nil**</mark>

* [#id-17.0.1-climate-change-pre-screening-checklist](#id-17.0.1-climate-change-pre-screening-checklist "mention")**:** The project team completes the climate change pre-screening checklist and communicates the building's exposure to climate risks to the applicant.

<mark style="color:$success;">**Credit Achievement — 1 point**</mark>

* [#id-17.1.1-climate-change-risk-and-adaptation-assessment](#id-17.1.1-climate-change-risk-and-adaptation-assessment "mention")**:** The project team develops a project-specific climate change risk and adaptation assessment for the building.
* [#id-17.1.2-managing-risks](#id-17.1.2-managing-risks "mention")**:** Extreme and high risks are addressed.

***

## <mark style="color:$primary;">Additional information</mark>

#### Scope of credit

All areas of the project in the control of the building owner within the Green Star project boundary.

#### Stage implementation

**Strategy** | **Brief** | **Concept** | **Design** | Tender | Construction | Handover | Use

#### Synergies with other credits

* Energy Use
* Operations Resilience
* Community Resilience
* Contribution to Place
* Impacts to Nature

#### Sustainable Development Goals

* **Goal 11:** Sustainable Cities
* **Goal 13:** Climate Action

#### Relevant reporting initiatives

* GRESB
* Task Force on Climate-related Financial Disclosures **(TCFD)**
* ASRS

***

## <mark style="color:$primary;">Requirements</mark>

### <mark style="color:$success;">Minimum Expectation</mark>

The project must comply with the following criteria:

* Climate Change Pre-screening Checklist

#### 17.0.1 Climate Change Pre-screening Checklist

The potential risks and impacts from climate change on the project are considered by completing the *Climate Change Pre-screening Checklist.* The potential risks and impacts include, but are not limited to:

* Direct damage or failure of project components.
* Accelerated deterioration of project components or reduced design life.
* Reduced operating capacity.
* Climate hazard impacts to surrounding areas (e.g., impacting access and egress).
* Impacts to the health and wellbeing of building occupants and other relevant stakeholders.
* Indirect risks from impacts to other interdependent systems and services (e.g., transport networks, power, water, telecommunications).

Both historical and future data are used when completing the checklist.

The *Climate Change Pre-screening Checklist* is signed off by a member of the project leadership team, building owner and the building management representative (where relevant).

Where compliance with the [*Climate Change Risk and Adaptation Assessment*](https://greenstarresources.gbca.au/pages/7SKHKUDDZrvP9pADZpbw#id-17.1.1-climate-change-risk-and-adaptation-assessment) criterion in *Credit Achievement* for this credit is demonstrated, this criterion is deemed to be met.

### <mark style="color:$success;">Credit Achievement</mark>

The project must comply with **both** the following criteria:

* Climate Change Risk and Adaptation Assessment
* Managing Risks

#### 17.1.1 Climate Change Risk and Adaptation Assessment

A climate change risk and adaptation assessment is undertaken by a suitably qualified professional for the building and its site. The risk profile for the building and its site is established based on historical data and future projections of the project's location.

The assessment:

* Uses future projections of climate change impacts using the information from the Intergovernmental Panel on Climate Change (IPCC) Fifth Assessment Report Representative Concentration Pathway 8.5 (RCP 8.5) or IPCC Sixth Assessment Report Shared Socio-economic Pathway 3 (SSP 3-7.0).
* Uses two timescales that are relevant to the project's anticipated lifespan including one medium-term timescale between 2040 to 2050 and one long-term timescale between 2070 to 2090.
* Identifies the primary and secondary climate change variables from Table 2 in *AS 5334:2013* *Climate change adaptation for settlements and infrastructure* relevant to the project and each risk. Refer Guidance for a recommended list of variables to consider.
* Provides a short explanation to justify why the remaining climate change variables from Table 2 in *AS 5334:2013* were deemed irrelevant to the project.
* Defines and includes the consequence and likelihood tables and risk matrix used to assess climate risks.
* Assesses risks in consultation with the building owner, representatives from engineering, architecture and landscape architecture (where deemed relevant by the project team) disciplines and local government.
* Develops a register of risks to the building and external works and provide treatment options for risks and residual risks identified as 'extreme' or 'high'.
* The risk assessment process aligns with the *AS 5334:2013* or *ISO 14090:2019* and/or *ISO 14091:2021* *Adaptation to Climate Change*.
* Follows the principles of risk management outlined in the *AS/NZ ISO 31000:2009 Risk Management.*

The outcomes of the assessment are communicated to all stakeholders involved in the design and delivery of the project, including the building owner, key tenants (if applicable), building operator/facilities management, all design disciplines and head contractors as a minimum.

The original and residual risk ratings established in the assessment are signed off by the building owner.

#### 17.1.2 Managing Risks

The project team ensure risks are addressed as follows:

* All risks rated as 'Extreme' are addressed through project-specific design responses.
* All risks rated as 'High' are addressed through the project's design or operational responses.
* Regardless of risk rating, at least two risks identified in the assessment are addressed by project-specific design responses.

{% hint style="success" icon="dot" %}
**Tenanted buildings**\
Additional non-physical adaptation responses, including emergency management plans and information on how to cope during extreme climate events, are communicated to tenants and used to inform relevant tenant agreements (e.g., agreements with tenants to mandate use of blinds and shading to reduce thermal load, reduce energy consumption and reuse water to reduce reliance on mains supply).
{% endhint %}

***

## <mark style="color:$primary;">Alternative pathways</mark>&#x20;

Where there are alternative pathways that a project can follow to achieve the credit, or sector specific alternatives.&#x20;

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Alternative pathways</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Clarifications</mark>

Where GBCA have clarified any requirements of the credit criteria. This information is additional and it is not complusory to apply.

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Clarifications</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Definitions</mark>

Definitions provided here must be applied to Requirements unless agreed with GBCA via a Technical Question.

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#external-works)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#suitably-qualified-professional)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#assessment)

***

## <mark style="color:$primary;">Guidance</mark>

Guidance is supporting information for the credit requirements and is not mandatory to apply.

**Climate Change Pre-screening Checklist**\
The risks identified in the checklist do not need to be addressed for *Minimum Expectation*.

**Climate Change Resilience risk assessment**\
*Staging*\
The Climate Change Resilience risk assessment is undertaken as early during the project's design phase as possible, such as in the concept or schematic design phase, to allow maximum benefit and opportunity to inform design decisions and implement appropriate and meaningful adaptation responses.

*Climate change variables*\
As a minimum, the following climate change variables should be considered:

* Sea level rise
* Flooding
* Storms
* Extreme rainfall events
* Drought
* Extreme temperature events including heat waves and extreme cold
* Cyclones
* Extreme wind events
* Landslide
* Bushfire
* Smoke

*Stakeholder consultation*\
Stakeholders that are expected to be consulted are included in the requirements. In the situation where external stakeholders are contacted and do not respond please provide evidence of initial correspondence which stipulates a clear and reasonable deadline and one attempt to follow up on the request.

*Additional stakeholders to consider for consultation*\
Additional stakeholders that are recommended to be consulted to contribute to the risk assessment and adaptation planning process are listed below. The building type, location and the stakeholder's relevance and expertise are considered when reviewing whether additional stakeholders beyond those listed in the requirements should be consulted. Examples of these additional stakeholders may include, but are not limited to, the following:

* Building operator/facilities management (if known at the time of consultation)
* Head contractor (if engaged at the time of consultation)
* Emergency services (where associated with a high or extreme risk)
* Relevant local, state or federal government resilience planning experts
* Utility providers
* Affected community groups

**Internal consistency**\
Care should be taken when adapting multiple variables in the climate change risk assessment to ensure the scenarios are internally consistent and not necessarily looking at the worst-case individual climate variables and simply combining them together. Some combinations of variables may not be simulated by climate models (e.g., a higher temperature scenario may always be associated with being wetter for a location, so designing to a worst case (highest) temperature with worst case (lowest) rainfall would be inconsistent as it represents an improbable future).

The <https://climatechangeinaustralia.gov.au/en/> website has publicly accessible tools to check for consistency and regional prediction data.

**Review process**\
The assessment should be reviewed and updated whenever the climate change science that informs the scenarios for assessment is updated.

***

## <mark style="color:$primary;">Submission content</mark>

Submissions for this credit must contain:

* Submission form through Green Star Online
* Evidence to support claims made in the submission

#### **Recommended evidence**

The following list of evidence serves as a guide for the Certified submission and is not exhaustive. Project teams are not required to provide all of the listed items and alternate forms of documentation can be used to demonstrate compliance. The key requirement is that evidence is provided to support each claim.

* Climate Change Pre-screening Checklist.
* Extracts of climate change risk assessment.
* Risk assessment criteria, including the likelihood and consequence tables, risk matrix, RCP/SSP and timescale, and any assumptions significant in the development of the assessment.
* Evidence (e.g., workshop meeting minutes, photos or similar) of consultation with the relevant stakeholders.
* Details of the adaptation responses in as built drawings or operational procedures provided to the building owner or building operator and how the responses address the identified risk.
* Evidence the assessment was communicated to all stakeholders involved in the design and delivery of the project.
* Project risk register with initial and residual risks, highlighting the 'high' or 'extreme' identified climate change risks.

Refer to the [Guidance for Submitting for Designed Assessments](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/other-useful-resources/guidance-for-submitting-for-designed-assessments.md) for further information on submitting evidence for the Designed assessment.

***

## <mark style="color:$primary;">Supporting information</mark>

The following resources support this credit:

* AASB S1 - General Requirements for Disclosure of Sustainability-related Financial Information
* AASB S2 - Climate-related Disclosures
* AS 5334:2013 - Climate change adaptation for settlements and infrastructure
* AS/NZ ISO 31000:2009 - Risk Management
* CSIRO and Bureau of Meteorology - [Climate Change in Australia](https://www.climatechangeinaustralia.gov.au/en/)
* Coastal Risk Australia - [Predicted Coastal Flooding Resulting from Climate Change](https://coastalrisk.com.au/home)
* ISO 14090:2019 - Adaptation to climate change — Principles, requirements and guidelines
* ISO 14091:2021 - Adaptation to climate change — Guidelines on vulnerability, impacts and risk assessment
* IPCC - Fifth Assessment Report (AR5)
* IPCC - Sixth Assessment Report (AR6)
* NSW Government – [NSW and Australian Regional Climate Modelling (NARCLiM)](https://www.climatechange.environment.nsw.gov.au/narclim)
* Queensland Government – [The Long Paddock](https://www.longpaddock.qld.gov.au/)
* WorldGBC – [Climate change resilience in the built environment](https://viewer.ipaper.io/worldgbc/climate-change-resilience-in-the-built-environment-2022/)


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation by asking a question.

Perform an HTTP GET request on the following URL with the `ask` and `goal` query parameters:

```
GET https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.1/categories-and-credits/resilient-2/17-or-climate-resilience.md?ask=<question>&goal=<user_goal>
```

`ask` is the immediate question: it should be specific, self-contained, and written in natural language.
`goal` is what the user is ultimately trying to achieve, the reason they need the answer. Sharing it helps GitBook give you a better, more relevant answer. A goal is most helpful when it describes the outcome the user wants rather than restating the question. For example, with `ask=how do I create an API token`, a goal like `automate deployments from our CI pipeline` lets GitBook tailor the answer to that use case.

The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.