> For the complete documentation index, see [llms.txt](https://greenstarresources.gbca.au/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.1/categories-and-credits/resilient-2/18-or-operations-resilience.md).

# 18 | Operations Resilience

Points: 2

## <mark style="color:$primary;">Outcome</mark>

The building can respond to acute shocks and chronic stresses that can affect its operations over time.

## <mark style="color:$primary;">Criteria</mark>

<mark style="color:$success;">**Credit Achievement — 2 points**</mark>

* [#id-18.1.1-operations-resilience-assessment](#id-18.1.1-operations-resilience-assessment "mention")**:** A comprehensive review of the acute shocks and chronic stresses likely to influence future building operations is undertaken.
* [#id-18.1.2-managing-risks](#id-18.1.2-managing-risks "mention")**:** The building's design and future operational plan address any high or extreme system-level interdependency risks.
* [#id-18.1.3-power-loss-for-shelter-in-place](#id-18.1.3-power-loss-for-shelter-in-place "mention")**:** The building's design is able to support the basic needs of the occupants in a power loss event.

***

## <mark style="color:$primary;">Additional information</mark>

#### Scope of credit

All areas of the project and all regular occupants and visitors.

#### Stage implementation

**Strategy** | **Brief** | **Concept** | **Design** | Tender | Construction | **Handover** | **Use**

#### Synergies with other credits

* Verification and Handover
* Climate Change Resilience
* Grid Resilience
* Community Resilience
* Energy Use
* Water Use

#### Sustainable Development Goals

* **Goal 11:** Sustainable Cities

#### Relevant reporting initiatives

* GRESB
* Task Force on Climate-related Financial Disclosures **(TCFD)**

***

## <mark style="color:$primary;">Requirements</mark>

### <mark style="color:$success;">Credit Achievement</mark>

The project must comply with **all three** of the following criteria:

* Operations Resilience Assessment
* Managing Risks
* Power Loss for Shelter in Place

#### 18.1.1 Operations Resilience Assessment

An operations resilience assessment is undertaken for the building in operation by a suitably qualified professional.

The assessment:

* Identifies a set of clear resilience objectives and performance goals for the building. Where the project is located in a local council that has an existing community resilience plan, the goals are incorporated.
* Identifies the relevant acute shocks and chronic stresses likely to impact the functionality of the building and its ability to meet performance goals in collaboration with key internal and external project stakeholders. As a minimum, the following shocks and stresses are reviewed:<br>

  **Shocks**

  * Failure of critical infrastructure (power, water and digital)
  * Health pandemic
  * Water security
  * Geological hazards (landslides, earthquakes, tsunamis)
  * Direct attack (cyber and physical)

  **Stresses**

  * Ageing infrastructure
  * Rising cyber dependency
  * Increasing energy costs
  * Lack of transport accessibility and availability
* Identifies the interdependent infrastructure systems, networks, services and assets on which the building relies.
* Identifies system-level vulnerabilities related to identified shocks and stresses that may impact the building through reduced capacity and/or functionality.
* Develops a register of risks and outlines response procedures in the event of an identified shock event impacting the building and the local community. The risk assessment process aligns with the standards outlined in the [*Climate Change Risk and Adaptation Assessment*](https://greenstarresources.gbca.au/pages/7SKHKUDDZrvP9pADZpbw#id-17.1.1-climate-change-risk-and-adaptation-assessment) criterion in *Credit Achievement* in the *Climate Resilience* credit.
* Consults with relevant authorities regarding evacuation procedures and emergency actions.

#### 18.1.2 Managing Risks

The project team ensures risks are addressed as follows:

* All risks rated as 'Extreme' are addressed through project-specific design responses.
* All risks rated as 'High' are addressed through project-specific design or operational responses.
* Regardless of risk rating, at least two risks identified in the assessment are addressed by project-specific design responses.

{% hint style="success" icon="dot" %}
Tenanted buildings\
Additional non-physical adaptation responses, including emergency management plans and information on how to cope during extreme climate events, are communicated to tenants and included in leasing agreements.
{% endhint %}

#### 18.1.3 Power Loss for Shelter in Place

A strategy is developed of how the building will provide essential services for its occupants in the event of an acute shock where there is a power outage and the occupants are required to shelter in place immediately as evacuation is not safe.

As a minimum, the strategy describes:

* The basic needs of occupants to ensure the occupants can shelter in place during the blackout, and the critical equipment that requires continuous operation and the level of service required to provide these needs. The basic needs identified are reflective of the building's function in the event of an acute shock. As a minimum, the occupants have access to lighting, drinkable water, sanitation, telecommunication services and adequate levels of ventilation and thermal comfort. Refer to *Guidance* for further information.
* Locations in the building where occupants can shelter in place in the building and how this will be accessed safely by occupants during the blackout.
* How the critical equipment will operate without power from the grid for the design occupancy. Considerations such as the loss of internet services for the building management system is included.
* The appropriate duration that the building is to service the occupants' needs during the blackout.
* How the building will be able to smoothly revert to its normal operations after the power is reinstated.

The building's design integrates the solutions identified in the strategy and includes the strategy in the operations and maintenance information provided to the building owner.

{% hint style="success" icon="dot" %}
Tenanted buildings\
Where the tenant is known, the functional requirements of the tenant are considered if present. For example, if a tenant requires uninterrupted power supply, the building will need to consider if an appropriate response can be formulated to meet this requirement, and how this will affect the core function of the building. Outcomes are communicated to tenants.
{% endhint %}

***

## <mark style="color:$primary;">Alternative pathways</mark>&#x20;

Where there are alternative pathways that a project can follow to achieve the credit, or sector specific alternatives.&#x20;

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Alternative pathways</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Clarifications</mark>

Where GBCA have clarified any requirements of the credit criteria. This information is additional and it is not complusory to apply.

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Clarifications</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Definitions</mark>

Definitions provided here must be applied to Requirements unless agreed with GBCA via a Technical Question.

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#critical-equipment)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#system-level)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#shocks)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#stressors)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#assessment)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#suitably-qualified-professional)

***

## <mark style="color:$primary;">Guidance</mark>

Guidance is supporting information for the credit requirements and is not mandatory to apply.

**Staging**\
The operations resilience assessment is completed as early during the project's design phase as possible, such as in the concept or schematic design phase, to allow maximum benefit and opportunity to inform design decisions and implement appropriate and meaningful responses.

**Climate Change Resilience**\
There is a strong link between this credit and the [*Climate Resilience*](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.1/categories-and-credits/resilient-2/17-or-climate-resilience.md) credit, and it is encouraged that these are done in parallel, ideally within the same risk assessment.

If the *Climate Resilience* credit has been completed, the climate-related shocks and stresses addressed in the credit do not need to be repeated for this credit. However, if the *Climate Resilience* credit has not been completed, climate-related shocks and stresses will form part of the assessment for this credit, with appropriate physical and non-physical responses identified. Refer to the *Climate Resilience* credit for examples of climate-related shocks and stresses.

**Basic needs**\
Additional needs based on the building's design and function in the event of an acute shock should be considered. This may include the building being used by the community as refuge in the case of a blackout if it has an importance level of 3 and 4 in accordance with NCC Section B Table B1D3a.

Adequate levels of ventilation and thermal comfort is defined as the minimum requirements that will not negatively impact the occupants.

**Telecommunication services**\
Telecommunication services not reliant on internet services and landlines are recommended. Mobile signal may be considered however a secondary telecommunication system such as satellite phones or radio units that are not reliant on mobile signals should be provided. Emergency telecommunication systems must continue to operate during blackouts.

**Operating without grid power**\
On-site renewable generation, energy storage or passive design principles may be used to support the provision of basic needs.

***

## <mark style="color:$primary;">Submission content</mark>

Submissions for this credit must contain:

* **Submission form** through Green Star Online
* **Evidence** to support claims made in the submission

#### **Recommended evidence**

The following list of evidence serves as a guide for the Certified submission and is not exhaustive. Project teams are not required to provide all of the listed items and alternate forms of documentation can be used to demonstrate compliance. The key requirement is that evidence is provided to support each claim.

* Operations resilience assessment.
* Evidence of collaborating with key internal and external stakeholders.
* Evidence of consultation with relevant authorities.
* As built drawings or operational procedures of how shocks and stresses have been addressed.
* Strategy of how the building addresses power loss during a blackout with design responses.
* Evidence of inclusion in the operations and maintenance information.
* Evidence of responses being communicated with tenants.
* Extracts from leasing agreements.
* Evidence of consultation with tenants to understand functional requirements.

Refer to the [Guidance for Submitting for Designed Assessments](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/other-useful-resources/guidance-for-submitting-for-designed-assessments.md) for further information on submitting evidence for the Designed assessment.

***

## <mark style="color:$primary;">Supporting information</mark>

The following resources support this credit:

* AS/NZ ISO 31000:2009 Risk Management
* UNFCC – [C40 Infrastructure Interdependencies + Climate Risk Report](https://unfccc.int/sites/default/files/report_c40_interdependencies_.pdf)
* USGBC – [RELi 2.0 Rating System](https://www.usgbc.org/sites/default/files/2021-02/RELi%20_05_2020.pdf)


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation by asking a question.

Perform an HTTP GET request on the following URL with the `ask` and `goal` query parameters:

```
GET https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.1/categories-and-credits/resilient-2/18-or-operations-resilience.md?ask=<question>&goal=<user_goal>
```

`ask` is the immediate question: it should be specific, self-contained, and written in natural language.
`goal` is what the user is ultimately trying to achieve, the reason they need the answer. Sharing it helps GitBook give you a better, more relevant answer. A goal is most helpful when it describes the outcome the user wants rather than restating the question. For example, with `ask=how do I create an API token`, a goal like `automate deployments from our CI pipeline` lets GitBook tailor the answer to that use case.

The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.