> For the complete documentation index, see [llms.txt](https://greenstarresources.gbca.au/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.1/categories-and-credits/resilient-2/21-or-grid-resilience.md).

# 21 | Grid Resilience

Points: 2

## <mark style="color:$primary;">Outcome</mark>

The building contributes to grid stability.

## <mark style="color:$primary;">Criteria</mark>

<mark style="color:$success;">**Credit Achievement — 2 points**</mark>

* [#id-21.1.1-demand-response](#id-21.1.1-demand-response "mention")**:** The building has a demand response strategy.

or

* [#id-21.1.2-passive-design-solutions](#id-21.1.2-passive-design-solutions "mention")**:** The building has reduced its reliance on grid energy through passive design.

***

## <mark style="color:$primary;">Additional information</mark>

#### Scope of credit

All centrally controlled building systems under the control of the building operator.

#### Stage implementation

**Strategy** | **Brief** | **Concept** | **Design** | Tender | Construction | **Handover** | **Use**

#### Synergies with other credits

* Verification and Handover
* Energy Use
* Energy Source
* Climate Resilience
* Operations Resilience

#### Sustainable Development Goals

* **Goal 7:** Affordable and Clean Energy
* **Goal 13:** Climate Action

#### Relevant reporting initiatives

* GRESB
* Task Force on Climate-related Financial Disclosures **(TCFD)**

***

## <mark style="color:$primary;">Requirements</mark>

### <mark style="color:$success;">Credit Achievement</mark>

The project must comply with **one** of the following criteria:

* Demand Response
* Passive Design Solutions

#### 21.1.1 Demand Response

#### *Energy Management and Information Systems*

In addition to the requirements in [*Credit Achievement*](https://greenstarresources.gbca.au/pages/vqD8Vh2UQ7bnU6H3SxjN#id-23a.1.1-renewable-ready) in the *Energy Source* credit, the energy management and information systems has:

* The ability to receive external control signals.
* A pre-programmed load shedding response that can be triggered by the facilities management or automatically triggers upon the receipt of an external signal.
* A demand management dashboard that shows the peak demand target, current, historical demand, the demand shedding priorities and enabling button alongside the critical performance characteristics (typically comfort temperature).

#### *Load Shedding Strategy*

The building can shed at least 10% of the annual peak grid electricity demand for at least 4 hours and this is tested during the building commissioning process. A load shedding strategy is developed and included in the operations and maintenance information provided to the building owner and facilities management.

As a minimum, the strategy identifies:

* The systems and how much they contribute to the demand reduction on grid electricity. This may be a combination of a reduced level of service from building systems and using on-site renewable generation. Where there is a reduced level of service from building systems, occupant amenity and the functioning of the building will not be negatively impacted.
* The communication strategy to notify occupants how they will be impacted on the day of a potential event.

On-site renewable generation is only considered to contribute to demand reduction if the project demonstrates one of the following:

* The on-site generation system can continue to provide power to the building when disconnected from the grid.
* No more than 30% of electricity generated during peak solar generation period is exported to the grid.
* There is an agreement with the network operator that explicitly allows exports greater than 30% of the electricity generated during peak solar generation periods.

{% hint style="success" icon="dot" %}
**Tenanted buildings**\
The annual peak grid electricity demand includes tenant energy use as per the Energy Use calculation guide (i.e. the most energy intensive fitout is assumed if fitout works are excluded from the rating) even if fitout works are excluded from the rating.\
\
Where there are systems that service tenanted spaces included in the strategy and are controlled centrally by the building operator, the leasing or sale contracts outline the load shedding strategies and what impacts these may have on tenant/s. If the strategy relies on tenant-controlled systems to contribute to demand reduction, this is triggered alongside the centrally controlled systems and there is an agreement with the tenant/s.
{% endhint %}

#### 21.1.2 Passive Design Solutions

The building has reduced reliance on grid energy through passive design by having all the following attributes:

* The facade demonstrates a 10% improvement over a reference building. The reference building is a building modelled to NCC 2022 Section J, or the version of the code applicable to the building's construction, whichever is later. The reference building is based on NCC J1V3 or the minimum requirements in NCC J4D2 to J4D7 using calculations in accordance with Method 2 when using Specification 37.
* No mechanical cooling or heating for at least 80% of the building's regularly occupied areas.
* The regularly occupied areas are less than 3,000m<sup>2</sup> and at least 20% of the building's GFA, excluding car parks.

This criterion cannot be targeted by Class 7b and 8 industrial buildings.

***

## <mark style="color:$primary;">Alternative pathways</mark>&#x20;

Where there are alternative pathways that a project can follow to achieve the credit, or sector specific alternatives.&#x20;

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Alternative pathways</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Clarifications</mark>

Where GBCA have clarified any requirements of the credit criteria. This information is additional and it is not complusory to apply.

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Clarifications</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Definitions</mark>

Definitions provided here must be applied to Requirements unless agreed with GBCA via a Technical Question.

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#annual-peak-electricity-demand)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#peak-solar-generation-period)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#occupant-amenity)

***

## <mark style="color:$primary;">Guidance</mark>

Guidance is supporting information for the credit requirements and is not mandatory to apply.

**Relationship with Energy Source**\
The requirements of this credit are intended to be complimentary to the [*Energy Source*](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.1/categories-and-credits/positive-3/22-or-energy-source.md) credit. Both credits take into consideration the changing landscape of the grid to one that will be made up of more renewables however the challenges and opportunities that arise are addressed differently.

The increase in renewables in the grid provides an opportunity for buildings to maximise their use of renewables. This is the opportunity that has influenced the *Energy Source* credit which aims to ensure the building has implemented systems and a load shifting strategy to set the building up to maximises the use of renewables.

Meanwhile the *Grid Resilience* credit focuses on the building's contribution to grid stability during operation to smooth out peaks in supply and demand and other related shocks. This is provided by buildings that are able to adjust their demand in response to the needs of the grid at a point in time. The same systems may contribute to demonstrating compliance with both credits however as the intent of the credit is different, the way the systems are used will be different.

**Alternate approaches**\
There are four key components to this credit:

* The degree to how much the building is impacting on the grid during peak times or similar shocks
* The opportunity for the building to provide short or on-demand flexibility to manage its energy consumption
* Aligning supply of unscheduled generation (wind, solar) and demand for energy
* The opportunity for the building to increase the grid's resilience during its peak

If alternative solutions exist that address two or more of these components, project teams are encouraged to contact GBCA to develop an alternative path.

**External control signals**\
External control signals include communications from the energy retailer for buildings that sign up to a demand response programs. Projects are not required to be signed up to a demand response program however the energy management system is able to receive these signals. This is to allow buildings to sign up for a demand response program in the future.

**Contributing systems**\
Examples of systems that could contribute demand shedding include, but are not limited to, HVAC, lighting, hot water and EV charging. The level of service of these systems can be temporarily reduced. On-site renewable generation and energy storage can also contribute to reducing peak demand. Energy storage solutions may be electricity storage (e.g., batteries) or thermal storage (e.g., chilled water tanks).

*Excluded systems*\
On-site diesel generators are not recognised for the purposes of this credit. While diesel generators may be an effective way to reduce demand on the grid, this credit is aiming to provide a best practice approach to delivering its outcome.

**On-site energy generation**\
This element of the credit aims to optimise energy generation onsite with the demand profile, either through demand response, sizing of renewables or using on-site energy storage solutions such as batteries. The purpose is not to unnecessarily reduce renewable energy generation. The intent is to encourage the availability of renewable energy at times of peak demand.

The 30% energy export has been calculated to allow for weekend energy export assuming there is no energy used onsite during that same period.

**Micro-grids**\
As the aim of this credit is for the building to work with the wider grid, a building connected to a micro-grid can use the flexibility and capacity of the micro-grid to optimise the building's impact on the wider grid.

The inclusion of micro-grids recognises precinct scale energy masterplans where some buildings have significantly higher renewable energy generation potential than it can use, such as industrial buildings. This allows buildings to export locally in a micro-grid that is designed to support the volume of energy trading, without impacting the wider electricity network.

***

## <mark style="color:$primary;">Submission content</mark>

Submissions for this credit must contain:

* **Submission form** through Green Star Online
* **Evidence** to support claims made in the submission

#### **Recommended evidence**

The following list of evidence serves as a guide for the Certified submission and is not exhaustive. Project teams are not required to provide all of the listed items and alternate forms of documentation can be used to demonstrate compliance. The key requirement is that evidence is provided to support each claim.

**Demand Response**

* Load shedding strategy.
* Extracts from energy modelling report of annual peak grid electricity demand.
* As built drawings highlighting building systems and on-site renewable generation systems.
* Evidence that the strategy has been implemented into building commissioning processes and tested.
* Extract of agreement with network operator.
* Extracts of leasing or sale contracts highlighting the inclusion of load shedding strategies and impacts.
* Extracts of agreement with tenants including details of their contribution and permission to be involved in the building's demand response strategy.

**Passive Design Solutions**

* Extracts from an energy modelling report.
* As built drawings demonstrating no mechanical cooling or heating and regularly occupied areas.

Refer to the [Guidance for Submitting for Designed Assessments](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/other-useful-resources/guidance-for-submitting-for-designed-assessments.md) for further information on submitting evidence for the Designed assessment.

***

## <mark style="color:$primary;">Supporting information</mark>

The following resources support this credit:

* AEMO – [Wholesale demand response mechanism](https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/market-operations/wdrm)
* Australian Renewable Energy Agency – [Demand response](https://arena.gov.au/renewable-energy/demand-response/)
* AS 4755.1 – Demand response capabilities and supporting technologies for electrical products. Part 1: Demand response frame and requirements for demand response enabling devices (DREDs)
* GBCA - [From net zero to zero: A discussion paper on grid-interactive buildings](https://gbca-web.s3.amazonaws.com/media/documents/grid-interactive-efficient-buildings-discussion-paper_Q0FoGV8.pdf)
* IEEE 2030.5 – Smart Energy Profile Application Protocol
* International Energy Agency - [Managing the Seasonal Variability of Electricity Demand and Supply](https://www.iea.org/reports/managing-the-seasonal-variability-of-electricity-demand-and-supply)
* Lawrence Berkeley National Laboratory – [Introduction to Commercial Building Control Strategies and Techniques for Demand Response](https://eta.lbl.gov/publications/introduction-commercial-building)


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation by asking a question.

Perform an HTTP GET request on the following URL with the `ask` and `goal` query parameters:

```
GET https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.1/categories-and-credits/resilient-2/21-or-grid-resilience.md?ask=<question>&goal=<user_goal>
```

`ask` is the immediate question: it should be specific, self-contained, and written in natural language.
`goal` is what the user is ultimately trying to achieve, the reason they need the answer. Sharing it helps GitBook give you a better, more relevant answer. A goal is most helpful when it describes the outcome the user wants rather than restating the question. For example, with `ask=how do I create an API token`, a goal like `automate deployments from our CI pipeline` lets GitBook tailor the answer to that use case.

The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.