> For the complete documentation index, see [llms.txt](https://greenstarresources.gbca.au/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.1/categories-and-credits/responsible/2-or-responsible-construction.md).

# 2 | Responsible Construction

Points: 1

## <mark style="color:$primary;">Outcome</mark>

The builder's construction practices reduce impacts and promote opportunities for improved environmental and social outcomes.

## <mark style="color:$primary;">Criteria</mark>

<mark style="color:$success;">**Minimum Expectation — Nil**</mark>

* [#id-2.0.1-environmental-management-system](#id-2.0.1-environmental-management-system "mention")**:** The head contractor has an environmental management system in place to manage its environmental impacts on site.
* [#id-2.0.2-environmental-management-plan](#id-2.0.2-environmental-management-plan "mention")**:** The head contractor has an environmental management plan to cover the scope of construction activities.
* [#id-2.0.3-construction-and-demolition-waste-diversion](#id-2.0.3-construction-and-demolition-waste-diversion "mention")**:** At least 80% of construction and demolition waste is diverted from going to landfill.
* [#id-2.0.4-sustainability-training](#id-2.0.4-sustainability-training "mention")**:** The head contractor provides training on the sustainability targets of the building.

<mark style="color:$success;">**Credit Achievement — 1 point**</mark>

In addition to *Minimum Expectation:*

* [#id-2.1.1-increased-construction-and-demolition-waste-diversion](#id-2.1.1-increased-construction-and-demolition-waste-diversion "mention")**:** At least 90% of construction and demolition waste is diverted from going to landfill, and waste contractors and facilities comply with the Green Star Construction and Demolition Waste Reporting Criteria.

***

## <mark style="color:$primary;">Additional information</mark>

#### Scope of credit

All areas of the project and all site works after the purchase of the site until practical completion. This includes any demolition, early works and/or main works.

#### Stage implementation

Strategy | Brief | Concept | **Design** | **Tender** | **Construction** | Handover | Use

#### Synergies with other credits

* Inclusive Construction Practices

#### Sustainable Development Goals

* **Goal 11:** Sustainable Cities
* **Goal 12:**  Responsible Consumption and Production

***

## <mark style="color:$primary;">Requirements</mark>

### <mark style="color:$success;">Minimum Expectation</mark>

The project must comply with **all four** of the following criteria:

* Environmental Management System
* Environmental Management Plan
* Construction and Demolition Waste
* Sustainability Training

#### 2.0.1 Environmental Management System

The head contractor/s for all site works have an Environmental Management System (EMS) in place that meets one of the following:

* For contracts valued at less than $10 million, the EMS complies with either the NSW Environmental Management System Guidelines or another recognised framework.
* For contracts valued at over $10 million, the EMS is audited and certified to AS/NZS ISO 14001, BS 7750 or the European Eco-Management and Audit Scheme (EMAS).

The EMS is stand-alone or part of an integrated management system and is valid for the duration of site activities completed from the date of purchase by the developer. The EMS includes actions related to the implementation of the EMP.

If the project has different head contractors for the demolition, early works and main works, the 'contract value' can be considered separately.

#### 2.0.2 Environmental Management Plan

A project-specific Environmental Management Plan (EMP) is developed and implemented for the full duration of all site works. The purpose of the EMP is to assist the head contractor/s and its service providers to manage environmental performance conditions and impacts arising from demolition, excavation and construction.

If the project has different head contractors for the demolition, early works and main works, each head contractor has an EMP.

#### 2.0.3 Construction and Demolition Waste Diversion

At least 80% of site waste from site works is diverted from landfill.

The waste contractors and processing facilities provide a Disclosure Statement outlining how the company and their reporting aligns with the *Green Star Construction and Demolition Waste Reporting Criteria.*

The mass of waste is reported (in kilograms or tonnes).

#### 2.0.4 Sustainability Training

Training is provided to at least 95% of contractors and subcontractors present on site for at least three days during all site works. The content of the training includes the following:

* Sustainability attributes of the project and their benefits.
* Value of certification.
* Role site worker/s play in delivering a sustainable building.

### <mark style="color:$success;">Credit Achievement</mark>

In addition to *Minimum Expectation*, the project must comply with the following criterion:

* Increased Construction and Demolition Waste Diversion

#### 2.1.1 Increased Construction and Demolition Waste Diversion

At least 90% of site waste from all site works is diverted from landfill.

The waste contractors and processing facilities comply with the *Green Star Construction and Demolition Waste Reporting Criteria* by providing the Compliance Verification Summary.

The mass of waste is reported (in kilograms or tonnes).

***

## <mark style="color:$primary;">Alternative pathways</mark>&#x20;

Where there are alternative pathways that a project can follow to achieve the credit, or sector specific alternatives.&#x20;

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Alternative pathways</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Clarifications</mark>

Where GBCA have clarified any requirements of the credit criteria. This information is additional and it is not complusory to apply.

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Clarifications</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Definitions</mark>

Definitions provided here must be applied to Requirements unless agreed with GBCA via a Technical Question.

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#early-works)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#excavation-waste)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#practical-completion)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#site-works)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#special-waste)

***

## <mark style="color:$primary;">Guidance</mark>

Guidance is supporting information for the credit requirements and is not mandatory to apply.

**Environmental management system**\
A formalised Environmental Management System (EMS) is a process that can be used to identify, manage, audit, and reduce environmental impacts, and generate reports on environmental performance progress. It should provide a systematic and methodical approach to preventing impacts and when they occur to planning, implementing, and reviewing an organisation's response.

The management system may be integrated with other management systems (such as occupational health and safety, risk registers etc.) to give a 'whole of business' approach.

All formalised EMS should follow the basic stages of high-level commitment, identification of impacts, review, target setting, action planning, monitoring, and reporting. The process is to be frequent and ongoing.

*Alternate recognised standard*

If projects wish to use an alternate standard to AS/NZS ISO 14001, BS 7750 or the European Eco-Management and Audit Scheme (EMAS), a Technical Question must be submitted. A demonstration of how the proposed standard aligns with one of the recognised standards is to be included.

**Environmental management plan**\
The NSW Environmental Management Systems Guidelines contains requirements of EMPs which is considered best practice.

**Site waste**\
Special waste and excavation waste, refer Definitions, are excluded from site waste. However, soil generated from site clean-up works which incorporates soil leaving the site mixed with general construction and demolition waste must be included in the waste-to-landfill calculations, as it forms part of the building site's general waste profile.

**Calculating waste**\
To calculate the amount of waste diverted from landfill, the project team is required to report the total amount of waste generated and the total amount of waste diverted from landfill.

Project teams are encouraged to use the Building Materials Reporting Tool Template to provide a more granular breakdown of their waste. The [Waste Avoided Leadership Challenge](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/leadership-challenges/lc9-or-waste-avoided.md)[ is available to recognise the use of this template.](#user-content-fn-1)[^1] Refer to [GBCA's Australia's Waste(d) Opportunity](https://gbca-web.s3.amazonaws.com/media/documents/australias-wasted-opportunity---2025-benchmarking-report.pdf) for further information.

**Volume to weight conversion**\
Waste contractors are often required to determine the weight of waste material streams from visual inspections of a load's volume for the purpose of reporting the estimated weights of material types removed from site (e.g., timber, steel, plasterboard, concrete, carpet).

The conversion factors in the table below may be used to convert measurement of waste types from volume to weight.

<table data-search="false"><thead><tr><th width="255">Material</th><th width="149.75">Density (tonne/m³)</th><th width="40">•</th><th width="223.333251953125">Material</th><th width="205.58349609375">Density (tonne/m³)</th></tr></thead><tbody><tr><td>Aluminium cans - whole</td><td>0.026</td><td></td><td>Commingled containers (plastic, glass, steel, and aluminium cans)</td><td>0.063</td></tr><tr><td>Aluminium cans - flattened</td><td>0.087</td><td></td><td></td><td></td></tr><tr><td>Aluminium cans - baled</td><td>0.154</td><td></td><td>Concrete</td><td>1.5</td></tr><tr><td>Asphalt / Bitumen</td><td>0.8</td><td></td><td>Garbage</td><td>0.15</td></tr><tr><td>Bricks</td><td>1.2</td><td></td><td>Garden / Vegetation</td><td>0.15</td></tr><tr><td>Car Batteries</td><td>0.375</td><td></td><td>Glass bottles - whole</td><td>0.174</td></tr><tr><td>Carpets</td><td>0.3</td><td></td><td>Glass bottles - semi-crushed</td><td>0.347</td></tr><tr><td>Cement Sheet</td><td>0.5</td><td></td><td>Green waste processed</td><td>0.3</td></tr><tr><td>Ceramics</td><td>1</td><td></td><td>Green waste unprocessed</td><td>0.15</td></tr><tr><td>Clean Soil</td><td>1.6</td><td></td><td>Hazardous Wastes</td><td>0.2</td></tr><tr><td>Cobbles / Boulders</td><td>1.4</td><td></td><td>Insulation</td><td>0.05</td></tr><tr><td>Litter trap</td><td>0.75</td><td></td><td>Plastic containers - whole, some flattened</td><td>0.013</td></tr><tr><td>Metals</td><td>0.9</td><td></td><td>Plastic containers - baled</td><td>0.139</td></tr><tr><td>Oil</td><td>0.8</td><td></td><td>Rubber</td><td>0.3</td></tr><tr><td>Other Textiles</td><td>0.15</td><td></td><td>Soil / Rubble&#x3C;150mm</td><td>1.4</td></tr><tr><td>Others</td><td>0.3</td><td></td><td>Steel cans - whole</td><td>0.052</td></tr><tr><td>Paint</td><td>0.8</td><td></td><td>Steel cans - flattened</td><td>0.13</td></tr><tr><td>Paper / Cardboard</td><td>0.1</td><td></td><td>Steel cans - baled</td><td>0.226</td></tr><tr><td>Plasterboard</td><td>0.2</td><td></td><td>Wood / Timber</td><td>0.3</td></tr><tr><td>Plastic containers - whole</td><td>0.01</td><td></td><td>Waste oil</td><td>0.8</td></tr></tbody></table>

*Source: Western Australia Waste Authority*

**GECA Construction and Demolition Waste Services Standard**\
Waste contractors and processing facilities that comply with the GECA Construction and Demolition Waste Services Standard (CDWSv1.0-2021) comply with the Green Star Construction and Demolition Waste Reporting Criteria.

**Sustainability Training**\
Evidence provided is to demonstrate a clear link between the sustainability training material presented and the records of attendance. Project teams are recommended to consider documentation revision, dates, and detailed attendance records to demonstrate specific training undertaken.

***

## <mark style="color:$primary;">Submission content</mark>

Submissions for this credit must contain:

* **Submission form** through Green Star Online
* **Evidence** to support claims made in the submission

#### Recommended evidence

The following list of evidence serves as a guide for the Certified submission and is not exhaustive. Project teams are not required to provide all of the listed items and alternate forms of documentation can be used to demonstrate compliance. The key requirement is that evidence is provided to support each claim.

**Environmental Management System**

* For contracts valued at less than $10 million, evidence demonstrating EMS complies with either the NSW Environmental Management System Guidelines or another recognised framework.
* For contracts valued at more than $10 million, evidence that the EMS has been certified to one of the recognised standards listed.
* Evidence that an EMS was in place for the duration of site activities.
* Evidence of site purchase date and any works that have been completed prior (if relevant)

**Environmental Management Plan**

* Extracts of the EMP/s that were in place for the duration of site activities.
* Evidence that the EMP complies with the EMS
* Copies of reporting required by the EMP – no less than two site audits for every 12 months of construction phase duration and covering every phase of construction (i.e., demolition, early / site preparation works and construction).

**Construction and Demolition Waste Diversion**

* Demolition or Site Drawings indicating the structures on site at time of purchase, extent of demolition and retained structure and façade.
* Cumulative waste report generated from the monthly waste reports provided by the waste contractor over the entire duration of construction and demolition works.
* Disclosure statement outlining how the contractor or facility aligns with the *Green Star Construction and Demolition Waste Reporting Criteria.*

**Sustainability Training**

* Evidence of sustainability training materials.
* Evidence of attendance (e.g., site induction register).
* Evidence that demonstrates the proportion of site workers that attended the training.

**Increased Construction and Demolition Waste Diversion**

* Compliance Verification Summaries from waste contractor(s) and waste processing facilities as detailed in the *Green Star Construction and Demolition Waste Reporting Criteria* document
* Auditor credentials as detailed in the *Green Star Construction and Demolition Waste Reporting Criteria* document

Refer to the [Guidance for Submitting for Designed Assessments](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/other-useful-resources/guidance-for-submitting-for-designed-assessments.md) for further information on submitting evidence for the Designed assessment.

***

## <mark style="color:$primary;">Supporting information</mark>

The following resources support this credit:

* AS/NZS ISO 14001 Environmental Management
* BS 7750 Specification for environmental management systems
* GBCA – [Green Star Construction and Demolition Waste Reporting Criteria](http://new.gbca.org.au/construction-and-demolition-waste/)
* GBCA – [Australia's Waste(d) Opportunity](https://gbca-web.s3.amazonaws.com/media/documents/australias-wasted-opportunity---2025-benchmarking-report.pdf)
* European Commission – Eco-Management and Audit Scheme (EMAS)
* NSW EPA – Environmental Management Systems Guidelines
* Western Australia Waste Authority – '[Converting Volumes to Tonnes](https://www.der.wa.gov.au/images/documents/our-work/consultation/current-consultation/Consultation%20Sheet%20-Approved%20method%20for%20recyclers.pdf)'

[^1]: **18/11/26**:&#x20;

    Ad-hoc: Updated to link to released Leadership Challenge


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation by asking a question.

Perform an HTTP GET request on the following URL with the `ask` and `goal` query parameters:

```
GET https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.1/categories-and-credits/responsible/2-or-responsible-construction.md?ask=<question>&goal=<user_goal>
```

`ask` is the immediate question: it should be specific, self-contained, and written in natural language.
`goal` is what the user is ultimately trying to achieve, the reason they need the answer. Sharing it helps GitBook give you a better, more relevant answer. A goal is most helpful when it describes the outcome the user wants rather than restating the question. For example, with `ask=how do I create an API token`, a goal like `automate deployments from our CI pipeline` lets GitBook tailor the answer to that use case.

The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.