> For the complete documentation index, see [llms.txt](https://greenstarresources.gbca.au/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.1/categories-and-credits/responsible/3-or-verification-and-handover.md).

# 3 | Verification and Handover

Points: 1

## <mark style="color:$primary;">Outcome</mark>

The building has been optimised and handed over to deliver a higher level of performance in operation.

## <mark style="color:$primary;">Criteria</mark>

<mark style="color:$success;">**Minimum Expectation — Nil**</mark>

* [#id-3.0.1-metering-and-monitoring](#id-3.0.1-metering-and-monitoring "mention")**:** The building is set up for optimum ongoing management due to its appropriate metering and monitoring systems.
* [#id-3.0.2-commissioning-and-tuning](#id-3.0.2-commissioning-and-tuning "mention")**:** The building has set environmental performance targets, designed and tested for airtightness, been commissioned, and will be tuned.
* [#id-3.0.3-building-information](#id-3.0.3-building-information "mention"): The project team creates and delivers operations and maintenance information to the facilities management team at the time of handover. Information is available to building users on how to best use the building.

<mark style="color:$success;">**Credit Achievement — 1 point**</mark>

In addition to *Minimum Expectation*:

* [#id-3.1.1-soft-landings-approach](#id-3.1.1-soft-landings-approach "mention")**:** The project uses a soft landings approach that involves the future facilities management team.

or

* [#id-3.1.2-independent-commissioning-agent](#id-3.1.2-independent-commissioning-agent "mention")**:** An independent level of verification is provided to the design, planning, commissioning and tuning activities through the involvement of an independent commissioning agent.

For large projects, both must occur.

***

## <mark style="color:$primary;">Additional information</mark>

#### Scope of credit

All building systems and envelope installed under the scope of the rating.

#### Stage implementation

Strategy | Brief | Concept | **Design** | **Tender** | **Construction** | **Handover** | **Use**

#### Synergies with other credits

* Energy Use
* Energy Source
* Grid Resilience
* Operations Resilience
* Clean Air

#### Sustainable Development Goals

* **Goal 11:** Sustainable Cities

***

## <mark style="color:$primary;">Requirements</mark>

### <mark style="color:$success;">Minimum Expectation</mark>

The project must comply with **all three** of the following criteria:

* Metering and Monitoring
* Commissioning and Tuning
* Building Information

#### 3.0.1 Metering and Monitoring

#### *Metering distribution*

The building has accessible energy and water metering for all distinct uses and major uses. Metering is provided for each separate tenancy or unit. Floor by floor metering is provided if the entire floor has a single use. Refer Guidance for further information for different building classes.

A metering schedule is provided in accordance with steps 7-10 in CIBSE's *TM39 Building Energy Metering* including energy and water meters.

#### *Metering and monitoring attributes*

All meters including utility meters and sub-meters:

* Provide continual information (up to 1-hour interval readings) to the connected monitoring system.
* Are commissioned and validated in accordance with the most current version of NABERS' *Metering and Consumption Rules.*
* Are pattern approved by the National Measurement Institute (NMI) or by another recognised standard. Refer Definitions for recognised standards.

An automatic monitoring system is implemented that provides reports on consumption trends and raises an alarm when the energy or water use increases beyond certain parameters and automatically issues an alert to the facilities manager.

For Class 2 build to sell apartments, only the consumption trends of the base building are provided to the facilities manager. Meters for each sole-occupancy unit are not required to be connected to the monitoring system.

{% hint style="success" icon="dot" %}
**Tenanted buildings**\
Where the base building metering and monitoring strategy relies on connection of tenant meters, project teams may use a tenancy fitout guide and model lease clauses to demonstrate tenant requirements regarding metering, including rules for connection of meters and programming of monitoring systems.
{% endhint %}

#### 3.0.2 Commissioning and Tuning

#### *Environmental performance targets and information*

Prior to schematic design, the project team sets and documents the environmental performance targets for the project in a design intent report or an owner's project requirements (OPR) document.

As a minimum, the report/document:

* Lists the targets for the project energy use, water consumption, indoor environment quality and the airtightness targets for the building.
* Outlines the operational monitoring expectations of energy, water and indoor environment quality.
* Is signed off by the building owner.

#### *Services and maintainability review*

Prior to construction, a services and maintainability review of the project is conducted. The review involves the building owner/building owner's representative, design consultants, architect, facilities manager, main works head contractor and the Independent Commissioning Agent (where nominated).

The review addresses the commissionability, controllability, maintainability, operability and safety of all systems and its outcomes are summarised in a Services and Maintainability Report.

All items are addressed, closed-out and documented within the final Services and Maintainability Report and are signed off by all involved parties.

#### *Building commissioning*

Prior to the start of construction works for the relevant trade packages, the process of commissioning, the identification of commissioning documentation and technical requirements for commissioning are included in the construction documentation.

During construction of the relevant trade packages, a commissioning plan is developed prior to the start of commissioning. The commissioning plan details the process, activities and program to commissioning the metering and monitoring system, for airtightness and all nominated building systems in accordance with a recognised commissioning standard or guideline (Refer *Definitions* for examples).

When the building is commissioned, it is completed in accordance with the same recognised commissioning standard or guideline.

#### *Airtightness*

Prior to schematic design, airtightness targets are set. The targets are defined by the project team are based on the [*ATTMA Australia Guide for Airtightness Targets*](https://www.bcta.group/attma/download/attma-australia-guide-to-air-tightness-targets/). The targets are included as part of the environmental performance targets and included in the energy modelling where relevant.

Prior to the end of design development, the air barrier system schematic is reviewed to identify and reduce risks to achieving airtightness targets.

Prior to the start of construction works, an approach to delivering airtightness is developed. It includes:

* An outline of responsibilities and coordination of relevant project team members and trades required to achieve targets.
* An airtightness testing and commissioning plan (included as part of the overall project commissioning plan) including approach for defect rectification.

Prior to practical completion, the building is subject to airtightness testing of the conditioned envelope. The testing is carried out by a suitably qualified practitioner in accordance with the latest revision of *AS/NZS ISO 9972 Method 1*. Airtightness testing is carried out on the whole building, or across a sample of areas of the whole building that are representative of the range of external envelope constructions, including different façade types, junctions and building geometries as recommended by a suitably qualified practitioner. Both typical assemblies as well as critical, or high-risk assemblies are tested.

Refer *Guidance* for further information on sampling areas for different building classes.

On sections smaller than the whole building, qualitative procedures such as *ASTM E1186-17* may be used.

All results are shared with the building owner, regardless of whether the airtightness targets have or have not been met. The airtightness test results are also included in the project's energy modelling. Where targets are not achieved, opportunities for improvement are also identified and shared with the building owner.

#### *Building systems tuning*

The building owner or developer contractually commits to a tuning process that includes quarterly adjustments and measurements for at least the first 12 months after occupation.

The commitment includes:

* A building tuning manual or plan
* A description of roles and responsibilities of the building tuning team

The building tuning plan can be detailed within the commissioning plan. Where the tuning plan or manual is separate to the commissioning plan, it refers to using the commissioning plan and the commissioning records and results as the baseline data.

The building tuning team includes:

* The facilities manager
* The Independent Commissioning Agent (ICA) or other building owner's representative
* The head contractor
* Subcontractors responsible for the mechanical, electrical and BMS as a minimum. Other subcontractors, where relevant, may be required.

#### 3.0.3 Building Information

#### *Operations and maintenance information*

The project team provides operations and maintenance information for all nominated building systems to the building owner (or designated representative).

As a minimum, the operations and maintenance information:

* Contains maintenance instructions including procedures, schedules and requirements, service contacts, warranties and as built mechanical, electrical and hydraulic drawings for all nominated building systems.
* The appropriate user group has access to the information they require to deliver best practice environmental outcomes.
* Includes guidance for the facilities management team on how to keep the information up to date and how to assess, correct and validate alerts or faults identified by the building's monitoring system.

#### *Building logbook*

A building logbook developed in accordance with *CIBSE TM31 Building Logbook Toolkit* and covers all nominated building systems is presented to the building owner (or designated representative) prior to project occupation.

#### *Building user information*

The project team provides building user information to the building owner and facilities management team prior to occupation.

As a minimum, the building user information:

* Is publicly available to the intended building users. The building users are the regular occupants and representatives of the building tenants.
* Includes information relevant to the target audience to support the everyday operations of the building. The information is communicated in a way that can be easily understood by the target audience.
* Is provided in an editable, digital format and is accessible to be updated and edited by the facilities management team, or other appropriate stakeholder groups.

### <mark style="color:$success;">Credit Achievement</mark>

In addition to *Minimum Expectation*, the project must comply with **one** of the following criteria:

* Soft Landings Approach
* Independent Commissioning Agent

For projects with a Total Building Services Value of over $20m, **both** requirements must be met.

#### 3.1.1 Soft Landings Approach

Stages 1 to 4 of the soft landings approach outlined in CIBSE ANZ's *The Soft Landings Framework Australia and New Zealand* are implemented on the project. The sample worksheets from CIBSE ANZ's *The Soft Landings Framework Australia and New Zealand* for Stage 1 to 3 are completed and actions for Stage 4 are identified.

The facilities management team (or building owner's representative) for the building is involved in the soft landings approach by:

* Being involved in commissioning and handover process.
* Taking part in the development of a brief technical guide for the building and the building operations and maintenance manual.
* Signing-off on the operations and maintenance manual.
* Being trained before handover. The training includes a demonstration of the building management system and any control mechanisms.

The facilities management team has continued access to critical design and construction team members for two years after practical completion to allow for transitioning the responsibility for the building.

#### 3.1.2 Independent Commissioning Agent

Prior to design development, an Independent Commissioning Agent (ICA) is appointed. The ICA advises, monitors and verifies the commissioning and tuning of the nominated building systems throughout design development, tender, construction, commissioning, and tuning phases.

The specified commissioning requirements is overseen by a qualified independent commissioning professional(s).

***

## <mark style="color:$primary;">Alternative pathways</mark>&#x20;

Where there are alternative pathways that a project can follow to achieve the credit, or sector specific alternatives.&#x20;

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Alternative pathways</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Clarifications</mark>

Where GBCA have clarified any requirements of the credit criteria. This information is additional and it is not complusory to apply.

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Clarifications</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Definitions</mark>

Definitions provided here must be applied to Requirements unless agreed with GBCA via a Technical Question.

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#air-barrier-system-schematic)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#automatic-monitoring-system)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#independent-commissioning-agent)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#nominated-building-systems)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#recognised-standard)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#building-services)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#suitably-qualified-professional)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#suitably-qualified-practitioner)

***

## <mark style="color:$primary;">Guidance</mark>

Guidance is supporting information for the credit requirements and is not mandatory to apply.

**Metering**

*Metering distribution*\
The following distribution of meters should be provided as a minimum when determining the extent of metering for the relevant building class space type:

<table><thead><tr><th width="214">Building class</th><th>Metering distribution</th></tr></thead><tbody><tr><td>Class 2 excluding build to rent</td><td><ul><li>One meter for energy and one meter for water is provided for all base building common areas and each sole-occupancy unit. Authority meters may be used.</li><li>Where hot water is provided centrally, water metering is provided for each sole-occupancy unit.</li><li>Additional sub-metering for energy and water is provided for each distinct use if a floor has multiple uses (e.g., if there is a swimming pool and a gym on the same floor, these are sub-metered separately).</li></ul></td></tr><tr><td>Class 2 build to rent and Class 3 spaces</td><td><ul><li>One meter for energy and one meter for water per floor if the entire floor has a single use.</li><li>Where hot water is provided centrally, a meter is provided per floor.</li><li>Additional sub-metering for energy and water is provided for each distinct use if a floor has multiple uses.</li></ul></td></tr><tr><td>Class 7b and 8 industrial spaces leased to tenants</td><td><ul><li>One meter for energy and one meter for water is provided for each tenancy.</li><li>Where a common energy use exceeds 5% of the total energy consumption of the building or 100kW, it is metered independently.</li><li>Where a common water use exceeds 10% of the total water use of the building, it is metered independently.</li></ul></td></tr><tr><td>Small buildings (GFA, excluding car parks, is less than 1000m²)</td><td><ul><li>One for energy and one for water.</li><li>Where there is specialist equipment with an annual power consumption of 100kW or more, it is metered independently.</li><li>If accessible to the building manager, the utility meter is acceptable provided it meets the Metering and monitoring attributes criterion.</li></ul></td></tr><tr><td>All other building classes</td><td><ul><li>One for energy and one for water per floor if the entire floor has a single use.</li><li><p>Additional sub-metering for energy and water is provided for each distinct use or tenant if a floor has multiple uses or tenancies.</p><ul><li>For Class 6 retail spaces, staff only areas are metered separately from retail areas due to different usage patterns.</li><li>For Class 9b education spaces, different learning spaces are metered separately (e.g., classrooms, assembly halls, lecture halls, laboratories etc.) due to different usage patterns.</li></ul></li><li>Where an energy load for a single item exceeds 5% of the total energy consumption of the building or 100kW, it is metered independently.</li><li>Where a common water use exceeds 10% of the total water use of the building, it is metered independently.</li></ul></td></tr></tbody></table>

Metering can be installed above and beyond the examples above.

Refer *CIBSE TM39 Building Energy Metering standard* for guidance on breaking down end uses.

*Metering schedule*\
The schedule includes the estimated loads for energy and water and lists:

* Incoming input (electricity, gas, water etc.);
* Outgoing energy or water (on-site solar export or non-potable water export);
* End use (lighting, HVAC etc.);
* Estimated energy consumption for the end use and which meters provide the required information; and
* Initial estimated end consumption.

Refer *CIBSE TM39 Building Energy Metering standard* for an example schedule and a template.

*CIBSE TM39 Building Energy Metering standard*\
Although this standard has been created to be used for developing energy metering and monitoring strategies, for the purpose of this credit, the same principles described in the Standard should be used for developing water metering and monitoring strategies.

**Operational monitoring expectations**

* Energy: Performance measurement procedures including quarterly reporting against targets.
* Water: Performance measurement procedures including quarterly reporting against targets.
* Indoor Environment Quality: can be via occupant comfort survey targets, HVAC system maintenance targets, quarterly reporting of indoor air quality, thermal comfort or lighting comfort performance measurements.

**Commissioning plan**\
For the commissioning plan, it is not enough to state that systems must be commissioned to the relevant standard. Details are to be provided.

**Airtightness**\
The intent of this criterion is to integrate attention to airtightness during the design and construction of the project to ensure it is considered meaningfully and is integrated into the commissioning process.

*Setting targets*\
Airtightness targets are set prior to schematic design. The intent of deciding these early in the design phase is to ensure the project team and building owner are in agreement on the goals of the project and will aid the meaningful integration of airtightness into the design.

The targets are to be based on the [*ATTMA Australia Guide for Airtightness Targets*](https://www.bcta.group/attma/download/attma-australia-guide-to-air-tightness-targets/). This means that where there is a recommended design air permeability target available for the project's building type, this target is used as a starting point to define a project-specific target. Project teams may then have specific project goals that could influence the starting value to result in a different value to be chosen as the final target (e.g., the project is aiming to retain as much of the existing building as possible therefore a less stringent target would be more appropriate). Different airtightness targets may be set for different compartments of the building based on the space function and the goals of the project.

*Reviewing the air barrier system*\
A review of the air barrier system is suggested in two phases during design:

* At schematic design phase: This includes creation of an air barrier system schematic, definitions of different space conditioning requirements, and delineation of the extent of the conditioned building envelope. This process should fit in the same timeline with other such building envelope commissioning steps, such as definition of fire separation boundaries in the building.
* Design development phase: A review for airtightness is completed. The air barrier system includes façade elements, but also interior separations between conditioned and unconditioned spaces, and integration of HVAC, electrical, communications, and plumbing elements into the system. This includes plan reviews for air barrier continuity on building plans, sections, and details. To be considered:
  * Constructability and construction sequence
  * Costs of completion of the air barrier system
  * Scope of work and necessary coordination between trades and responsibilities

*Relevant project team members and trades*\
This includes architects and building designers, façade and mechanical/services engineers, airtightness consultant, the head contractor, Independent Commissioning Agent (ICA) (if appointed), services contractors and installers and airtightness testers.

*Commissioning plan*\
Airtightness is considered in the commissioning plan where stages of commissioning for airtightness are defined. The plan should include builder and mechanical contractor statements of understanding and commitment of resources and personnel necessary for, and commitment to assist with, airtightness test preparation, regardless of scale of planned testing.

*Testing for airtightness*\
The aim of the airtightness testing is to understand how the building envelope has performed against the airtightness targets set.

Project teams conducting partial testing should do so prior to the envelope being fully completed, to provide early indication of weak points and allow time to address any issues identified during the testing process. Such tests may be considered qualitative and evaluate the effectiveness of the air barrier system. Nearer project completion, a quantitative test such as a *AS/NZS ISO 9972:2015* on a whole building may also be used.

If a sample of areas is being tested, the following are suggested for the relevant building class:

<table><thead><tr><th width="220.25">Building class</th><th>Sampling areas</th></tr></thead><tbody><tr><td>Class 2 and 3 buildings</td><td><p>Testing should be completed on a minimum of 10 dwelling units or 10% of the total number of dwelling units, whichever is greater. The sample of units includes:</p><ul><li>A representative of the lower-most, upper-most, and intermediate floors;</li><li>A representative of the external envelope construction including different façade types and building geometries;</li><li>A representative of each apartment typology (by number of bedrooms, Accessibility/DDA etc.);</li><li>The unit with lowest-performing NatHERS rating.</li></ul></td></tr><tr><td>All other building classes</td><td>Testing should be completed on a total of either 5,000m² or 20% of the building's envelope area, whichever is greater.</td></tr></tbody></table>

The quantitative tests are recommended to be filed with ATTMA Lodgement for verification of tester qualification, equipment calibration, and calculation methods and a Certificate of Air Permeability Test is provided.

*Opportunities for improvement*\
Where targets are not achieved, opportunities of improvement are included as part of the commissioning process as far as practically possible and the design is reviewed with the project design team to share any lessons learnt for future projects with the project team and building owner.

**Building user information**\
As the building user information is to be provided in an editable, digital format that can be updated when needed, a digital format is recommended when displaying the information to the intended building users. This may be in the format of digital signage, interactive information kiosks, induction or training material, a website and/or a mobile application.

**Soft landings**\
The intent of soft landings is to reduce the gaps between predicted and achieved performance and create a smooth transition into use. The CIBSE framework outlines 5 stages. Stage 5 is optional, but highly encouraged.

**Multiple project roles – GSAP and ICA**\
In some cases, the GSAP's employer may also be engaged in other roles on the Green Star project. This does not constitute a conflict of interest where individuals are able to perform each role independently to meet the requirements of each credit. For example, an organisation may fulfil the role of both GSAP and Independent Commissioning Agent (ICA) however the individuals are different and the ICA is not involved in the Green Star strategy and vice versa.

In this case, project teams should confirm that there is no conflict of interest by including relevant discussion in the submission.

***

## <mark style="color:$primary;">Submission content</mark>

Submissions for this credit must contain:

* **Submission form** through Green Star Online
* **Evidence** to support claims made in the submission

#### Recommended evidence

The following list of evidence serves as a guide for the Certified submission and is not exhaustive. Project teams are not required to provide all of the listed items and alternate forms of documentation can be used to demonstrate compliance. The key requirement is that evidence is provided to support each claim.

**Metering and Monitoring**

* As built drawings showing the location of all energy and water meters and the associated energy and water uses.
* Metering schedule.
* Evidence that all distinct and major uses are metered with calculations to support estimates.
* Letter of confirmation from the contractor/metering provider/manager demonstrating that the metering systems are continually and automatically monitored by a system that is able to produce alerts if any inaccuracies are found
* Completed metering validation documents to demonstrate metering system meets the NABERS rules for validation.
* Product data sheets or similar to demonstrate pattern approval by the NMI or that the meters meet another recognised standard.
* Extracts from commissioning reports demonstrating correct operation of meter reading, reporting and alarm generation.

**Commissioning and Tuning**

* Extracts from design intent report or OPR highlighting environmental performance targets and airtightness targets.
* Evidence to demonstrate a services and maintenance review was conducted prior to construction.
* Extracts from Service and Maintainability Report, where the service and maintainability review is summarised and all items are listed, addressed and closed-out.
* Extracts from the commissioning report demonstrating that comprehensive pre-commissioning activities and commissioning activities have been performed.
* Extracts of commissioning plan.
* Evidence of how airtightness targets were determined.
* Evidence of air barrier system schematic review (e.g., marked up drawings) and that it is completed prior to the end of design development.
* Building airtightness testing report detailing air flow rates, details of design for airtightness and other relevant details or a copy of the project's ATTMA Green Star Commissioning for Air Tightness report.
* Extracts from energy modelling report.
* Signed confirmation from the building owner that the results have been sighted.
* A summary of recommendations for improvements provided to the building owner (where relevant).
* Extracts of building tuning plan and roles and responsibilities.
* A commitment or contract from the building owner and head contractor demonstrating that there is a requirement for a building tuning process.

**Building Information**

* Extracts of operations and maintenance information.
* Building logbook.
* Building user information.
* Evidence that the operations and maintenance information and building logbook are provided to the building owner.
* Evidence that building user information is provided to the building owner and facilities management in an editable format.

**Soft Landings Approach**

* Evidence of implementation of CIBSE ANZ framework.

**Independent Commissioning Agent**

* CV of the Independent Commissioning Agent detailing the qualifications and experience relevant to the project.
* Letter from building owner confirming the appointment of an ICA.
* Evidence to demonstrate that the ICA was involved from the design stage through to tuning.

Refer to the [Guidance for Submitting for Designed Assessments](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/other-useful-resources/guidance-for-submitting-for-designed-assessments.md) for further information on submitting evidence for the Designed assessment.

***

## <mark style="color:$primary;">Supporting information</mark>

The following resources support this credit:

* AIRAH DA27 – Building Commissioning 2011
* AIRAH DA28 – Building Management and Control Systems (BMCS) 2011
* ASHRAE Guideline 0-2019 – [The Commissioning Process](https://store.accuristech.com/ashrae/standards/guideline-0-2019-the-commissioning-process?product_id=2076120)
* ASHRAE Commissioning Guideline 1.1-2007 – [HVAC\&R Technical Requirements for The Commissioning Process](https://store.accuristech.com/ashrae/standards/guideline-1-1-2007-hvac-r-technical-requirements-for-the-commissioning-process?ashrae_auth_token=\&utm_campaign=86628\&utm_content=86628\&utm_medium=landingpage\&utm_source=promotion\&utm_term=86628\&gateway_code=ashrae\&product_id=1573306)
* ASHRAE Standard 202-2024 – [The Commissioning Process Requirements for New Buildings and New Systems](https://store.accuristech.com/ashrae/standards/ashrae-202-2024?product_id=1573306\&ashrae_auth_token=\&utm_campaign=86628\&utm_content=86628\&utm_medium=landingpage\&utm_source=promotion\&utm_term=86628\&gateway_code=ashrae)
* AS/NZS ISO 9972:2015 Thermal performance of buildings – Determination of air permeability of buildings – Fan pressurisation method
* ASTM E779-10 Standard test method for determining air leakage rate by fan pressurisation
* ATTMA – [ATTMA Australia Guide to Air Tightness Targets](https://www.bcta.group/attma/download/attma-australia-guide-to-air-tightness-targets/)
* BSRIA Soft Landings Framework
* CIBSE – [TM39 Building energy metering](https://www.cibse.org/knowledge-research/knowledge-portal/tm39-building-metering-and-monitoring-2026/)
* CIBSE – Commissioning Code M (and the ancillary codes for relevant services)
* CIBSE – [Soft Landings Framework – Australia and New Zealand](https://www.cibse.org/knowledge-research/knowledge-portal/soft-landings-framework-australia-and-new-zealand/)
* NABERS – [Metering and Consumption Rules](https://www.nabers.gov.au/publications/metering-and-consumption-rules)
* NIBS Guideline 3-2012 – National Institute of Building Sciences Building Enclosure Commissioning Process BECx
* SA TA 5342:2021 – Standards Australia Technical Specification for Building Commissioning


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation by asking a question.

Perform an HTTP GET request on the following URL with the `ask` and `goal` query parameters:

```
GET https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.1/categories-and-credits/responsible/3-or-verification-and-handover.md?ask=<question>&goal=<user_goal>
```

`ask` is the immediate question: it should be specific, self-contained, and written in natural language.
`goal` is what the user is ultimately trying to achieve, the reason they need the answer. Sharing it helps GitBook give you a better, more relevant answer. A goal is most helpful when it describes the outcome the user wants rather than restating the question. For example, with `ask=how do I create an API token`, a goal like `automate deployments from our CI pipeline` lets GitBook tailor the answer to that use case.

The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.