> For the complete documentation index, see [llms.txt](https://greenstarresources.gbca.au/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.1/categories-and-credits/responsible/5-or-responsible-procurement.md).

# 5 | Responsible Procurement

Points: 1

## <mark style="color:$primary;">Outcome</mark>

The procurement process for key products, materials, and services for the building's design and construction follows best practice environmental and social principles.

## <mark style="color:$primary;">Criteria</mark>

<mark style="color:$success;">**Credit Achievement — 1 point**</mark>

* [#id-5.1.1-risk-and-opportunity-assessment](#id-5.1.1-risk-and-opportunity-assessment "mention")**:** The building's design and construction procurement processes follow ISO 20400 Sustainable Procurement – Guidance by undertaking a risk and opportunities assessment.
* [#id-5.1.2-responsible-procurement-plan](#id-5.1.2-responsible-procurement-plan "mention")**:** A responsible procurement plan is developed to mitigate risks and implement opportunities identified in the assessment.

***

## <mark style="color:$primary;">Additional information</mark>

#### Scope of credit

All materials and products specified in the project's design and construction procurement processes. It does not include operational procurement decisions.

#### Stage implementation

**Strategy** | Brief | **Concept** | **Design** | **Tender** | **Construction** | Handover | Use

#### Synergies with other credits

* Responsible Structure
* Responsible Envelope
* Responsible Systems
* Responsible Finishes
* Procurement and Workforce Inclusion
* Inclusive Construction Practices

#### Sustainable Development Goals

* **Goal 8:** Decent Work and Economic Growth
* **Goal 10:** Reduced Inequalities
* **Goal 12:**  Responsible Consumption and Production

#### Relevant reporting initiatives

* GRESB
* Modern Slavery

***

## <mark style="color:$primary;">Requirements</mark>

### <mark style="color:$success;">Credit Achievement</mark>

The project must comply with **both** of the following criteria:

* Risk and Opportunity Assessment
* Responsible Procurement Plan

#### 5.1.1 Risk and Opportunity Assessment

Prior to appointment of the head contractor for the main works, a project-specific risk and opportunities assessment is completed by the project design team with input from the building owner.

The assessment:

* Identifies 10 or more key items in the project's supply chain with at least two building services and at least one building material.
* Identifies and evaluates the environmental, social and human health risks, and opportunities for each key item and within the supply chain, such as in the extraction, manufacture, or transport of key materials. As a minimum, the risks and opportunities in the following issues, as described in Clause 4.3 in *ISO 20400:2017 Sustainable Procurement – Guidance*, are analysed and prioritised:

  * Human rights
  * Labour practices
  * The environment
  * Fair operating practices
  * Consumer issues
  * Community involvement and development

  Refer to Annexes A in *ISO 20400:2017* for further guidance.

#### 5.1.2 Responsible Procurement Plan

A responsible procurement plan is developed by the project design team to manage the risks and implement the opportunities identified in the risk and opportunity assessment.

The plan:

* Identifies project-level environmental, social, economic objectives to manage the risks and implement the opportunities identified in the risk and opportunities assessment.
* Outlines requirements for data collection and impact measurement, monitoring and reporting. Refer to Clause 6.5 in *ISO 20400:2017* for further guidance.
* Provides a framework for incentivising the achievement of the plan with relevant contractors and trades.

The plan is embedded in tender documentation for the head contractor and relevant trades. Where the head contractor is engaged under a design and construct contract, the responsible procurement plan is developed prior to procurement activities and embedded in tender documentation for subcontractors and relevant trades. The head contractor is involved in developing the responsible procurement plan.

During construction, the plan is implemented in partnership with relevant contractors and trades, demonstrating data collection, monitoring, and reporting has been carried out. Refer to Clause 7 in *ISO 20400:2017* for further guidance.

***

## <mark style="color:$primary;">Alternative pathways</mark>&#x20;

Where there are alternative pathways that a project can follow to achieve the credit, or sector specific alternatives.&#x20;

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Alternative pathways</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Clarifications</mark>

Where GBCA have clarified any requirements of the credit criteria. This information is additional and it is not complusory to apply.

These were previously referred to as *Frequently Asked Questions*.&#x20;

<details>

<summary>Clarifications</summary>

Existing FAQs are currently located [*here*](https://www.gbca.org.au/greenstar-manager/faqs/). GBCA are working on bringing them across to this site. New FAQs will be published here under the relevant credit and type.

</details>

***

## <mark style="color:$primary;">Definitions</mark>

Definitions provided here must be applied to Requirements unless agreed with GBCA via a Technical Question.

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#building-materials)

[Glossary](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/all-definitions.md#building-services)

***

## <mark style="color:$primary;">Guidance</mark>

Guidance is supporting information for the credit requirements and is not mandatory to apply.

**ISO 20400 Sustainable Procurement – Guidance**\
*ISO 20400:2017 Sustainable Procurement – Guidance* provides guidance to organisations, independent of their activity or size, on integrating sustainability within procurement. It identifies the principles and core subjects of sustainable procurement and considerations to managing risks and opportunities. It also describes how sustainability considerations are integrated within the procurement practices of an organisation and the organisational conditions and management techniques to implement sustainable procurement. The last section sets out the procurement process itself, including planning, sourcing and contract management.

It is expected that the design team, head contractor and sub-contractors follow *ISO 20400:2017* to manage procurement risk in their supply chains to meet the requirements of this credit. It is not expected that all organisations downstream in the supply chain, such as suppliers, follow *ISO 20400:2017* as the guidance is for stakeholders involved in procurement decisions. Suppliers may wish to review the guidance to understand how to improve sustainability in their procurement practices however this is outside the scope of this credit.

**Risk and opportunity assessment**\
The risk and opportunities assessment must be completed by the project design team and building owner prior to appointing the head contractor of the main works. The intent of this is to ensure that the building owner provides input into the analysis and prioritisation of the risks and opportunities relevant to the project.

Where the head contractor of the main works identifies an additional building service or material to the key items identified in the risk and opportunities assessment prior to procurement activities, the head contractor should provide an equivalent assessment of the risks and opportunities to demonstrate the item has an equivalent or improved risk and opportunity profile with the input of the building owner. A procurement plan for the item is also developed as per the Responsible Procurement Plan criterion.

**Responsible procurement plan**\
This can be part of an organisational plan or a stand-alone plan.

***

## <mark style="color:$primary;">Submission content</mark>

Submissions for this credit must contain:

* **Submission form** through Green Star Online
* **Evidence** to support claims made in the submission

#### Recommended evidence

The following list of evidence serves as a guide for the Certified submission and is not exhaustive. Project teams are not required to provide all of the listed items and alternate forms of documentation can be used to demonstrate compliance. The key requirement is that evidence is provided to support each claim.

**Risk and Opportunity Assessment**

* Extracts from risk and opportunity assessment.

**Responsible Procurement Plan**

* Responsible procurement plan.
* Extracts from tender documents demonstrating responsible procurement plan was incorporated for at least 10 items.
* Extracts of impact and data reporting undertaken through the construction process in partnership with relevant trades and contractors.

Refer to the [Guidance for Submitting for Designed Assessments](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/other-useful-resources/guidance-for-submitting-for-designed-assessments.md) for further information on submitting evidence for the Designed assessment.

***

## <mark style="color:$primary;">Supporting information</mark>

The following resource supports this credit:

* [ISO 20400: Sustainable Procurement – Guidance](https://www.iso.org/standard/63026.html)


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation by asking a question.

Perform an HTTP GET request on the following URL with the `ask` and `goal` query parameters:

```
GET https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/green-star-buildings/v1.1/categories-and-credits/responsible/5-or-responsible-procurement.md?ask=<question>&goal=<user_goal>
```

`ask` is the immediate question: it should be specific, self-contained, and written in natural language.
`goal` is what the user is ultimately trying to achieve, the reason they need the answer. Sharing it helps GitBook give you a better, more relevant answer. A goal is most helpful when it describes the outcome the user wants rather than restating the question. For example, with `ask=how do I create an API token`, a goal like `automate deployments from our CI pipeline` lets GitBook tailor the answer to that use case.

The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.