> For the complete documentation index, see [llms.txt](https://greenstarresources.gbca.au/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/leadership-challenges/lc9-or-waste-avoided.md).

# LC9 | Waste Avoided

Leadership  - Developed in partnership with Coreo

***Points: 2***&#x20;

## <mark style="color:$primary;">Outcome</mark>

The project reports on all materials leaving site from project commencement to handover and reduces materials wasted.

## <mark style="color:$primary;">Rating tool applicability</mark>

* Green Star Buildings v1.1
* Green Star Buildings v1
* Green Star – Design & As Built (all versions)

## <mark style="color:$primary;">Why is this Leadership Challenge Important?</mark>

The Australia’s Waste\[d] Opportunity 2025 report by circular economy leaders Coreo, in partnership with the Green Building Council of Australia (GBCA), reveals that Australia’s construction industry is sending billions of dollars of valuable materials to waste - and calls for urgent change across the built environment sector.

Australia’s Waste\[d] Opportunity 2025 analysed 145 construction and fitout projects across the country and found that for every square metre built, an average of 141 kilograms of material is wasted, costing an estimated $389 per square metre.¹

Given the Federal Government’s target of 1.2 million new homes by 2029, that’s $64 billion in wasted materials over the next five years. The report reveals that while 83% of projects claim high rates of material diversion from landfill, actual material recovery is far lower - with plastic recovery, for example, as low as 14%. The findings call into question the reliability of current reporting practices and urge a shift toward benchmarks that prioritise reuse, circularity, and genuine recovery.

This Leadership Challenge responds to that gap by asking projects to move beyond headline diversion rates and provide clearer, more useful information about what leaves site, where it goes, and what outcome is achieved. By improving the quality and consistency of material outflows reporting, project teams can better identify avoidable waste, make more informed decisions during design, procurement, construction and handover.

The challenge also encourages project teams to reduce waste before it is generated. This includes considering whether materials already on site can be reused, selecting products and systems that minimise offcuts and over-ordering, and choosing materials with credible end-of-life pathways. In doing so, projects can support better data collection, improve transparency across the supply chain, and help shift the industry from managing waste after the fact to avoiding material loss in the first place.

¹ Australia’s Waste\[d] Opportunity 2025, Coreo in partnership with the Green Building Council of Australia, 2025.

## <mark style="color:$primary;">Criteria</mark>

<mark style="color:$success;">**Credit Achievement — 1 point**</mark>

* [#lc9.1.1-material-outflows-reporting](#lc9.1.1-material-outflows-reporting "mention")**:** Material outflows from the building are reported.
* [#lc9.1.2-on-site-separation](#lc9.1.2-on-site-separation "mention")**:** At least four material streams are separated on-site, enabling higher recovery rates.
* [#lc9.1.3-off-site-reuse](#lc9.1.3-off-site-reuse "mention")**:** At least 10% of the total material outflows are verified as being reused off-site, supported by chain-of-custody evidence.

<mark style="color:$success;">**Exceptional Performance — 1 point**</mark>

* [#lc9.2.1-comprehensive-reporting](#lc9.2.1-comprehensive-reporting "mention")**:** Material outflows from the building are reported by material/product type and their outcomes.
* [#lc9.2.2-reduced-wasted-materials](#lc9.2.2-reduced-wasted-materials "mention")**:** The building's waste materials from deconstruction/demolition through to construction completion are 10% less than a benchmark.

***

## <mark style="color:$primary;">Additional information</mark>

**Stage Implementation:** Concept · Design · Tender · Construction · Handover

### Synergies with other credits

* Responsible Construction
* Responsible Procurement
* Life Cycle Impacts

### Sustainable Development Goals

* **Goal 12:**  Responsible Consumption and Production

***

## <mark style="color:$primary;">Requirements</mark>

### <mark style="color:$success;">Credit Achievement</mark>

The project must comply with **all** the following criteria:

* Material Outflows Reporting
* On-site Separation
* Off-site Reuse

#### LC9.1.1 Material Outflows Reporting

The quantity and type of materials that leave the project site (material outflows) is reported during the construction project using the Building Materials Reporting Tool.

The report includes:

* **Scope of works:** Identify which of the below phases are included in the project scope:
  * Demolition/deconstruction phase
  * Construction phase
* **Material outflows by phase:** The following details are reported against the relevant project phases outlined above. Metrics include:
  * the total volume (m³) of materials removed from site
  * reconciliation with waste contractor invoices and collection records, including:
    * date of removal
    * volume Collected in m³
    * project phase (demolition/deconstruction or construction)
* **Facility distribution identification:** The head contractor, sub-contractor or waste contractor, provides a list of where materials are taken directly after leaving the construction site. These include:
  * reprocessing facilities
  * transfer stations, including potential destinations of materials post sorting
  * reuse destinations, e.g. second-hand sellers, charities etc.

#### LC9.1.2 On-site Separation

At least four material streams are separated on site, (e.g. there is a bin for metals, another for plasterboard, another for timber, etc all separate from mixed waste bins), enabling higher recycling rates.

Each single material stream bin on-site is:

* clearly labelled with what can and cannot go into the bin
* accessible across the site
* not commingled (only a single material type goes into the bin).

Inductions and/or toolbox training sessions are provided so that all contractors understand the on-site separation requirement.

The head contractor is responsible for managing and tracking separation, including booking collections (where applicable) and retaining supporting records.

Where a load is rejected or noted as contaminated, the waste contractor provides a contamination note (or equivalent record). Corrective actions are managed at the head contractor’s discretion.

#### LC9.1.3 Off-site Reuse

Using the Building Materials Reporting Tool, at least 10% of the total material outflows volume (m³) is verified as being reused off-site, supported by chain-of-custody evidence.

Reuse percentage is calculated as:

$$
\text{Verified off-site reuse volume (m³)} \div \text{total material outflow volume (m³)} \times 100 = \text{reuse percentage (%)}
$$

### <mark style="color:$success;">Exceptional Performance</mark>

The project must comply with **all** the following criteria:

* Comprehensive Reporting
* Reduced Wasted Materials

#### LC9.2.1 Comprehensive Reporting

#### *Reporting*

Using the Building Materials Reporting Tool, project teams track material outflows across the project lifecycle by:

* Forecasting expected material outflows before works begin (i.e. before demolition/deconstruction), to identify opportunities to retain material value.
* Reporting actual outflows during demolition/deconstruction and construction, including material/product type, quantity, project phase and outcome.
* Explaining data collection and processes for handling material outflows.
* Evaluating results post construction are complete by comparing forecasts with actual outcomes and recording lessons lear

#### *Head contractor-led outflow management*

The head contractor is responsible for material outflow management across the project (rather than material removal and reporting by individual trades). This includes:

* Coordinating bin strategy and placement (including any single material stream bins).
* Booking collections (where applicable) and managing logistics so collections are efficient and controlled.
* Ensuring consistent data capture (phase allocation, volumes, and destinations) and retaining supporting records.
* Providing inductions/toolbox messaging so all trades follow the on-site separation approach and understand how material outflows are managed on the project.

#### LC9.2.2 Reduced Wasted Materials

Using the Building Materials Reporting Tool, the project demonstrates that total wasted materials are 127 kg/m² GFA or less, representing at least a 10% reduction against the benchmark of 141 kg/m² GFA.

***

## <mark style="color:$primary;">Guidance</mark>

Guidance is supporting information for the credit requirements and is not mandatory to apply.

**Why this credit uses “material outflows”**\
The Australia’s Waste\[d] Opportunity 2025 report supports a move away from treating materials as “waste” only once they leave site, and toward tracking the flow, value and outcome of materials. “Material outflows” is a useful term because it captures all materials leaving site, whether they are reused, recycled or sent to landfill.

**The Building Materials Reporting Tool**\
The Building Materials Reporting Tool is available on the [Green Star resources portal](https://www.gbca.org.au/greenstar-manager/resources/).

**Reduced wasted materials**\
The benchmark is drawn from Australia’s Waste\[d] Opportunity 2025 report, which analysed 92 building construction projects across Australia.

***

## <mark style="color:$primary;">Definitions</mark>

Definitions provided here must be applied to the Requirements unless agreed with GBCA via a Technical Question.

**Material outflows**\
Materials leaving site due to demolition/deconstruction and construction works, during the project.

**Wasted materials**\
Materials leaving site due to demolition/deconstruction and construction works during the project and sent to landfill, a waste-to-energy facility or recycling facility.

**Demolition/deconstruction phase material outflows**\
Removal of existing materials from site in the demolition/deconstruction phase of a refurbishment project.

**Construction phase material outflows**\
Removal of offcuts, packaging, surplus products and other materials removed from site during building construction.

**Off-site reuse**\
Items or materials kept in use through sale, donation, supplier take-back, refurbishment, remanufacture or repurposing after leaving the site.

**On-site separation**\
A material stream kept separate at source from mixed waste so it can be directed to an appropriate reuse or recycling pathway

**Reuse/reused**\
For this credit, an item is considered ‘reused’ where it falls into one of the following categories:

* **Reused as-is (direct reuse)**\
  The repeated use of a product for its original intended purpose without significant modification. Minor cleaning, adjustments, or minor repairs may be undertaken to enable continued use.
* **Refurbished**\
  A product returned to good working condition through repair, replacement of worn components, or aesthetic improvements. Performance is restored but not necessarily to an “as-new” condition.\
  Refurbished items are comprised predominantly of non-virgin materials.
* **Repurposed**\
  A product or component adapted for a different function or application than its original intended use, with limited reprocessing or modification. Repurposed items are comprised predominantly of non-virgin materials.
* **Remanufactured**\
  A product that has been re-engineered to an “as-new” condition, with performance equal to or exceeding its original specification. Remanufacturing typically involves complete disassembly, inspection, repair or replacement of worn components, and reassembly to a certified standard. Remanufactured items are comprised predominantly of non-virgin materials.

> Note: While the term reuse is commonly used in industry to refer only to direct reuse (for example, as defined by the Ellen MacArthur Foundation and ISO 59004:2024), this credit intentionally adopts a broader definition to recognise the environmental benefits of retaining products and materials in use, even where refurbishment, repurposing, or remanufacturing has occurred.

**Transfer station**\
A facility that accepts and processes mixed materials, then separates materials into separate streams to be sent to reprocessing facilities, landfill, or waste-to-energy.

**Reprocessing facility**\
Businesses that trade in specific waste material types for the purpose of transforming (recycling) it into new products.

***

## <mark style="color:$primary;">Submission content</mark>

#### Submission for this credit must contain:

* **Submission form** through Green Star Online
* **Waste Avoided submission template** (for Green Star Buildings v1.1 projects)
* **Building Materials Reporting Tool** (attach as part of evidence)
* **Evidence** to support claims made in the submission

#### Recommended evidence

The following list of evidence serves as a guide for the Certified submission and is not exhaustive. Project teams are not required to provide all of the listed items and alternate forms of documentation can be used to demonstrate compliance. The key requirement is that evidence is provided to support each claim.

**Material Outflows Reporting**

* Evidence (such as an invoice or collection record) showing that a project subcontractor or contractor used listed receiving facilities.
* Evidence (such as an invoice or collection record) of collection dates, quantities and collection types.

**Off-site Reuse**

* Evidence (such as an invoice or collection record) showing that items have been sent for off-site reuse.

**On-site Separation**

* Evidence (such a waste management plan and site photographs, invoices or collection records) showing material streams have been separated on-site.
* Evidence of inductions and/or toolbox training sessions provided so all contractors understand the on-site separation requirement.
* Evidence that the head contractor managed and tracked separation.

**Comprehensive Reporting and Reduced Wasted Materials**

* Evidence of client/building owner sign off on forecasted material outflows and plan.
* Evidence of data collection processes basis.
* Evidence of collections, weight basis and outcomes (reuse, recycling etc) such as invoices and collection records.

Refer to the Guidance for Submitting for Designed Assessment available on the Green Star resources portal for further information on submitting evidence for the Designed assessment.

***

## <mark style="color:$primary;">Supporting information</mark>

The following resources support this credit:

* Coreo, GBCA – [‘Australia’s Waste\[d\] Opportunity 2025’](https://gbca-web.s3.amazonaws.com/media/documents/australias-wasted-opportunity---2025-benchmarking-report.pdf)
* Western Australia Waste Authority – ‘Converting Volumes to Tonnes’


---

# Agent Instructions
This documentation is published with GitBook. GitBook is the documentation platform designed so that both humans and AI agents can read, navigate, and reason over technical content effectively. Learn more at gitbook.com.

## Querying This Documentation
If you need additional information that is not directly available in this page, you can query the documentation by asking a question.

Perform an HTTP GET request on the following URL with the `ask` and `goal` query parameters:

```
GET https://greenstarresources.gbca.au/greenstarresources.gbca.au_ratingtools/current-green-star-rating-tools/leadership-challenges/lc9-or-waste-avoided.md?ask=<question>&goal=<user_goal>
```

`ask` is the immediate question: it should be specific, self-contained, and written in natural language.
`goal` is what the user is ultimately trying to achieve, the reason they need the answer. Sharing it helps GitBook give you a better, more relevant answer. A goal is most helpful when it describes the outcome the user wants rather than restating the question. For example, with `ask=how do I create an API token`, a goal like `automate deployments from our CI pipeline` lets GitBook tailor the answer to that use case.

The response will contain a direct answer to the question and relevant excerpts and sources from the documentation.

Use this mechanism when the answer is not explicitly present in the current page, you need clarification or additional context, or you want to retrieve related documentation sections.